Recital 2
(2) Notwithstanding the necessity and binding timelines, experience has shown that many investments aiming to complete the TEN-T are confronted with complex and varied permit -granting procedures, cross-border procurement procedures and other procedures. This situation jeopardises the on time implementation of projects and in many cases results in significant delays and increased costs. In order to address these issues and make synchronised TEN-T completion possible,, harmonised action is necessary at Union level.
2018/10/19
Committee: TRAN
Amendment 53 #
Proposal for a regulation
Recital 10
(10) Cross-border TEN-T infrastructure projects face particular challenges as regards the coordination of permit granting procedures. The European Coordinators should be empowered to monitor these procedures and facilitate their synchronisation and completion in good time, respecting the deadline set in this Regulation.
2018/10/19
Committee: TRAN
Amendment 92 #
Proposal for a regulation
Article 3 – paragraph 3
(3) To ensure efficient and effective administrative procedures related to projects of common interest, project promoters and all authorities concerned shall ensure that the most rapid treatment legally possible is given to these projectsse projects are processed within an optimum legal timeframe, including as regards the resources allocated.
2018/10/19
Committee: TRAN
Amendment 111 #
Proposal for a regulation
Article 5 – paragraph 2 – subparagraph 1 – introductory part
The responsibility of the single competent authority referred to in paragraph 1 and/or the tasks related to it may be delegated to, or carried out by, another authority for carrying-out at the appropriate administrative level, per project of common interest or per particular category of projects of common interest, under the following conditions:
2018/10/19
Committee: TRAN
Amendment 128 #
Proposal for a regulation
Article 5 – paragraph 4
(4) When taking the comprehensive decision, the single competent authority shall ensure that the relevant requirements under international and Union law are respected and shall duly justify its decision on the basis of the applicable legal provisions.
2018/10/19
Committee: TRAN
Amendment 134 #
Proposal for a regulation
Article 6 – paragraph 2
(2) The pre-application phase, covering the period from the start of the permit granting procedure to the submission of the complete application file to the single competent authority, shall in principle not exceed two year20 months.
2018/10/19
Committee: TRAN
Amendment 145 #
Proposal for a regulation
Article 6 – paragraph 4 – introductory part
(4) Within threewo months of the start of the permit granting procedure, the single competent authority, in close cooperation with the project promoter and other authorities concerned and taking into account the information submitted by the project promoter on the basis of the notification referred to in paragraph 3, shall establish and communicate to the project promoter a detailed application outline, containing:
2018/10/19
Committee: TRAN
Amendment 159 #
Proposal for a regulation
Article 6 – paragraph 6
(6) The project promoter shall submit the application file based on the detailed application outline within the period of 218 months from the receipt of that detailed application outline. After the expiry of that period, the detailed application outline is no longer considered applicable, unless the single competent authority decides to prolong that period, on the basis of a justified request from the project promoter.
2018/10/19
Committee: TRAN
Amendment 167 #
Proposal for a regulation
Article 6 – paragraph 8
(8) The single competent authority shall assess the application and adopt a comprehensive decision within the period of one year10 months from the date of submission of the complete application file in accordance with paragraph 7. Member States may set an earlier time-limit, where appropriate.
2018/10/19
Committee: TRAN
Amendment 170 #
Proposal for a regulation
Article 7 – paragraph 1
(1) For projects that involve two or more Member States, the competent authorities of the Member States concerned shall align their timetables and agree on a joint schedule of specific arrangements for implementing the projects.