8 Amendments of Ivo BELET related to 2011/0300(COD)
Amendment 84 #
Proposal for a regulation
Article 9 – paragraph 2 – point b a (new)
Article 9 – paragraph 2 – point b a (new)
(b a) collaborative scheme: the comprehensive decision may encompass multiple individual legally binding decisions issued by the Competent Authority and other authorities concerned. The competent authority shall, in consultation with the other authorities concerned establish, on a case-by-case basis, a reasonable time limit within which the individual decisions can be issued, as well as the resulting total permitting time limit. The competent authority shall monitor the compliance of the time limits by the authorities concerned. If the decision by the authority involved is expected not to be delivered within the time limit, that authority shall inform the competent authority forthwith and include a justification for the delay.
Amendment 116 #
Proposal for a regulation
Annex III – part 1 – point 1 – paragraph 1
Annex III – part 1 – point 1 – paragraph 1
(1) For electricity projects falling under the categories set out in point 1 of Annex II, each Group shall be composed of representatives of the competent authorities of the Member States, national regulatory authorities, transmission system operators following their obligation to cooperate on a regional level in accordance with Article 6 of Directive 2009/72/EC and Article 12 of Regulation (EC) No 714/2009 and project promoters concerned by each of the relevant priorities designated in Annex I, as well as the Commission, the Agency and the ENTSO for Electricity.
Amendment 117 #
Proposal for a regulation
Annex III – part 1 – point 1 – paragraph 2
Annex III – part 1 – point 1 – paragraph 2
For gas projects falling under the categories set out in point 2 of Annex II, each Group shall be composed of representatives of the competent authorities of the Member States, national regulatory authorities, transmission system operators following their obligation to cooperate on a regional level in accordance with Article 7 of Directive 2009/73/EC and Article 12 of Regulation (EC) No 715/2009 and project promoters concerned by each of the relevant priorities designated in Annex 1, as well as the Commission, the Agency and the ENTSO for Gas.
Amendment 118 #
Proposal for a regulation
Annex III – part 1 – point 1 – paragraph 3
Annex III – part 1 – point 1 – paragraph 3
For oil and carbon dioxide transport projects falling under the categories referred to in Annex II(3) and (4), each Group shall be composed of the representatives of the competent authorities of the Member States, project promoters concerned by each of the relevant priorities designated in Annex 1 and the Commission.
Amendment 457 #
Proposal for a regulation
Article 9 – paragraph 2 a (new)
Article 9 – paragraph 2 a (new)
2a. collaborative scheme: the comprehensive decision may encompass multiple individual legally binding decisions issued by the Competent Authority and other authorities concerned. The competent authority shall, in consultation with the other authorities concerned establish, on a case-by-case basis, a reasonable time limit within which the individual decisions can be issued, as well as the resulting total permitting time limit. The competent authority shall monitor the compliance of the time limits by the authorities concerned. If the decision by the authority involved is expected not to be delivered within the time limit, that authority shall inform the competent authority forthwith and include a justification for the delay.
Amendment 704 #
Proposal for a regulation
Annex III – part 1 – point 1 – paragraph 1
Annex III – part 1 – point 1 – paragraph 1
(1) For electricity projects falling under the categories set out in point 1 of Annex II, each Group shall be composed of representatives of the competent authorities of the Member States, national regulatory authorities, transmission system operators following their obligation to cooperate on a regional level in accordance with Article 6 of Directive 2009/72/EC and Article 12 of Regulation (EC) No 714/2009 and project promoters concerned by each of the relevant priorities designated in Annex I, as well as the Commission, the Agency and the ENTSO for Electricity.
Amendment 709 #
Proposal for a regulation
Annex III – part 1 – point 1 – paragraph 2
Annex III – part 1 – point 1 – paragraph 2
For gas projects falling under the categories set out in point 2 of Annex II, each Group shall be composed of representatives of the competent authorities of the Member States, national regulatory authorities, transmission system operators following their obligation to cooperate on a regional level in accordance with Article 7 of Directive 2009/73/EC and Article 12 of Regulation (EC) No 715/2009 and project promoters concerned by each of the relevant priorities designated in Annex 1, as well as the Commission, the Agency and the ENTSO for Gas.
Amendment 714 #
Proposal for a regulation
Annex III – part 1 – point 1 – paragraph 3
Annex III – part 1 – point 1 – paragraph 3
For oil and carbon dioxide transport projects falling under the categories referred to in Annex II(3) and (4), each Group shall be composed of the representatives of the competent authorities of the Member States, project promoters concerned by each of the relevant priorities designated in Annex 1 and the Commission.