(3) ‘civil works’ means every outcome of building or civil engineering works taken as a whole that is sufficient in itself to fulfil an economic or technical function and entails including construction, as well as works consisting of reconstruction, installation, renovatione, or more elements of a physical infrademolition of a building structure;
Amendment 197 #
Proposal for a regulation
Article 2 – paragraph 2 – point 5 – point b
Article 2 – paragraph 2 – point 5 – point b
(b) they have legal personality or are entitled to legal capacity according to the provisions of the law;
Amendment 198 #
Proposal for a regulation
Article 2 – paragraph 2 – point 6
Article 2 – paragraph 2 – point 6
(6) ‘in-building physical infrastructure’ means physical infrastructure or installations at the end user’s location, including elements under joint ownership e.g. tenants' co-ownership, intended to host wired and/or wireless access networks, where such access networks are capable of delivering electronic communications services and connecting the building access point with the network termination point;
Amendment 202 #
Proposal for a regulation
Article 2 – paragraph 2 – point 9
Article 2 – paragraph 2 – point 9
(9) ‘major renovation and reconstruction works’ means building or civil engineering works at the end user’s location encompassing structural modifications of the entire in- building physical infrastructure or a significant part thereof and that require a building permit;
Amendment 216 #
Proposal for a regulation
Article 3 – paragraph 1
Article 3 – paragraph 1
1. USubject to paragraph 3 of this article, upon written request of an operator, public sector bodies owning or controlling physical infrastructure or network operators shall meet all reasonable requests for access to that physical infrastructure under fair and reasonable terms and conditions, including price, with a view to deploying elements of very high capacity networks or associated facilities. Public sector bodies owning or controlling physical infrastructure shall meet all reasonable requests for access also under non-discriminatory terms and conditions. Such written requests shall specify the elements of the physical infrastructure for which the access is requested, including a specific time frame.
Amendment 245 #
Proposal for a regulation
Article 3 – paragraph 3 – subparagraph 1 – point c
Article 3 – paragraph 3 – subparagraph 1 – point c
(c) the existence of safety and scientifically-based public health concerns;
Amendment 268 #
Proposal for a regulation
Article 4 – paragraph 1 – subparagraph 1 – introductory part
Article 4 – paragraph 1 – subparagraph 1 – introductory part
In order to request access to physical infrastructure in accordance with Article 3, any operator shall have the right to access, upon request, the following minimum information on existing physical infrastructure in electronic format via a single information point or directly from network operators and public sector bodies:
Amendment 342 #
Proposal for a regulation
Article 7 – paragraph 5 – subparagraph 2
Article 7 – paragraph 5 – subparagraph 2
The completeness of the application for permits or rights of way shall be determined by the competent authorities within 15 working days from the receipt of the application. Unless the competent authorities invited the applicant to provide any missing information within that period, the application shall be deemed complete.
Amendment 378 #
Proposal for a regulation
Article 7 – paragraph 11 a (new)
Article 7 – paragraph 11 a (new)
11a. The Commission will monitor the implementation of this Article in the Member States, and the Member States will report annually to the Commission the status of their implementation and if the listed conditions are met;