BETA

7 Amendments of Vittorio PRODI related to 2011/0399(COD)

Amendment 412 #
Proposal for a regulation
Article 22 – paragraph 3
3. A single reimbursement rate of the eligible costs shall be applied per action for all activities funded therein. The maximum rate shall be fixed in the work programme or work planis defined as outlined in the paragraphs 4 and 5.
2012/07/03
Committee: ITRE
Amendment 413 #
Proposal for a regulation
Article 22 – paragraph 3 – table (new)
Type of Method of Cost All Participants: Activity Calculation Universities, RTOs/Other, SME and Industry Research Total direct 100% + 30% eligible costs+flat rate Activities Total direct 70% + 40% foreseen at art eligible costs+flat 22 § 5 rate
2012/07/03
Committee: ITRE
Amendment 453 #
Proposal for a regulation
Article 22 – paragraph 5 a (new)
5a. The choice of the reimbursement rate applies to all actions, in all calls of Horizon 2020 and equally to all participants in an action. The reimbursement rates for actions mixing research and activities mentioned in Article 22 5(a) and 5(b), shall be determined by the nature of each activity as defined in each work package.
2012/07/03
Committee: ITRE
Amendment 454 #
Proposal for a regulation
Article 22 – paragraph 5 a (new)
5a. The reimbursement of full management activities', such as coordination, logistic, organization, management advise and supervision shall be identified in a specific work package and considered as direct costs and it is submitted to the rules applied for actions for which they have been incurred either at a maximum of 100% or up to 70%. The amount of this work package for the management costs shall not exceed 7% of the overall budget dedicated to the action.
2012/07/03
Committee: ITRE
Amendment 471 #
Proposal for a regulation
Article 23 – paragraph 1
1. Conditions for eligibility of costs aIn order to be considered eligible, direct costs incurred in the implementation of an action must meet the following conditions: (i) They must have been incurred defined in Article X of Regulation (EU) No xx [the Financial Regulation/Delegated Regulation]. Costs incurred by third parties under the action may be eligible according to the provisions of this Regulation and of the grant agreement. uring the implementation of the action, must include full salary and the costs of research infrastructure that are considered as direct costs, with the exception of final reports where provided for in the grant agreement; (ii) They must have been determined as actual costs in accordance with the usual accounting and management principles and practices of the participants; (iii) Participants will be authorised to use the rates accepted by national authorities for comparable activities on condition that they have obtained a certification on the methodology from an independent auditor; (iv) They must have been used for the sole purpose of achieving the objectives of the action and its expected results, in a manner consistent with the principles of economy, efficiency and effectiveness; (v) They must be recorded in the accounts of the participants and, in the case of any contribution from third parties, they must be recorded in the accounts of the third parties; (vi) They must ensure that the principle of non-discrimination applies to all employees.
2012/07/03
Committee: ITRE
Amendment 488 #
Proposal for a regulation
Article 24 – paragraph 1
1. Indirect eligible costs shall be determinreimbursed by applying a flat rate of 230% of the total direct eligible costs, excluding direct eligible costs for subcontracting and the costs of resources made available by third parties which are not used on the premises of the beneficiary, as well as financial support to third parties.
2012/07/03
Committee: ITRE
Amendment 498 #
Proposal for a regulation
Article 24 – paragraph 1 a (new)
1a. For the actions mentioned in Article 22(5), indirect costs shall be reimbursed by applying a flat rate of 40% of the total direct eligible costs, excluding the costs of resources made available by third parties which are not used on the premises of the beneficiary, as well as financial support to third parties.
2012/07/03
Committee: ITRE