REPORT on the proposal for a Council regulation on Union support for the nuclear decommissioning assistance programmes in Bulgaria, Lithuania and Slovakia PDF (361 KB) DOC (469 KB)
2016/11/22
Committee: ITRE
Dossiers: 2011/0363(NLE)
Documents: PDF(361 KB) DOC(469 KB)

Amendments (12)

Amendment 11 #
Proposal for a regulation
Recital 4
(4) In line with the Accession Treaty obligations and with the support of Community assistance, Bulgaria, Lithuania and Slovakia have closed the nuclear power plants and made significant progress towards their decommissioning. Further work is necessary in order to continue the progress with the actual dismantling operations until an irreversible state within the safe decommissioning process is reached,emolition, decontamination and dismantling operations and to implement the steady process towards the decommissioning end state whilst ensuring that the highest safety standards are applied. Based on the available estimates, completion of decommissioning work will require substantial additional financial resources.
2012/11/16
Committee: BUDG
Amendment 13 #
Proposal for a regulation
Recital 4 a (new)
(4a) The premature shutdown and consequent decommissioning of the Ignalina Power Plant with two 1500 MW RBMK reactor units inherited from the Soviet Union is of an unprecedented nature and represents for Lithuania an exceptional financial burden not commensurate with the size and economic strength of the country, Protocol No. 4 states that the Union assistance under the Ignalina Programme will be seamlessly continued and extended beyond 2006, for the period of next financial perspectives. This extended programme will be based on the same elements and principles as during the 2004-2006 and 2007-2013 periods.
2012/11/16
Committee: BUDG
Amendment 24 #
Proposal for a regulation
Article 2 – paragraph 1
1. The general objective of the Programme is to assist the Member States concerned to reach an irreversible state withinimplement the steady process towards the decommissioning processend state of Kozloduy units 1 to 4, Ignalina units 1 and 2 and Bohunice V1 units 1 and 2 nuclear power plants, in accordance with their respective decommissioning plans, while keeping the highest level of safety.
2012/11/16
Committee: BUDG
Amendment 32 #
Proposal for a regulation
Article 3 – paragraph 1 – subparagraph 2 – point b
(b) EUR [229 629 000] for the Ignalina Programme for the period 2014 to 201720;
2012/11/16
Committee: BUDG
Amendment 33 #

Recital 4
(4) In line with the Accession Treaty obligations and with the support of Community assistance, Bulgaria, Lithuania and Slovakia have closed the nuclear power plants and made significant progress towards their decommissioning. Further work is necessary in order to continue the progress with the actual dismantling operations until an irreversible state within the safe decommissioning process is reached,emolition, decontamination and dismantling operations and to implement the steady process towards the decommissioning end state whilst ensuring that the highest safety standards are applied. Based on the available estimates, completion of decommissioning work will require substantial additional financial resources.
2012/10/04
Committee: ITRE
Amendment 36 #

Recital 4 a (new)
(4a) Recognising that the premature shutdown and consequent decommissioning of the Ignalina Power Plant with two 1500 MW RBMK reactor units inherited from the Soviet Union is of an unprecedented nature and represents for Lithuania an exceptional financial burden not commensurate with the size and economic strength of the country, Protocol No. 4 states that the Union assistance under the Ignalina Programme will be seamlessly continued and extended beyond 2006, for the period of next financial perspectives. This extended programme will be based on the same elements and principles as during the 2004-2006 and 2007-2013 periods.
2012/10/04
Committee: ITRE
Amendment 39 #
Proposal for a regulation
Article 4 – paragraph 1 – point a
(a) Comply with Union's acquis; in particular in the area of nuclear safety the transposition into national law of the Council Directive 2009/71/Euratom on nuclear safety and the Council Directive 2011/70/Euratom on the management of spent fuel and radioactive waste.deleted
2012/11/16
Committee: BUDG
Amendment 51 #
Proposal for a regulation
Article 8 – paragraph 1
1. No later than end 20157, an evaluation report shall be established by the Commission on the achievement of the objectives of all the measures, at the level of results and impacts, the efficiency of the use of resources and its Union added value, in view of a decision amending or suspending the measures. The evaluation shall additionally address the scope for simplification, its internal and external coherence, the continued relevance of all objectives. It shall take into account evaluation results on the long-term impact of the predecessor measures.
2012/11/16
Committee: BUDG
Amendment 71 #

Article 2 – paragraph 1
1. The general objective of the Programme is to assist the Member States concerned to reach an irreversible state withinimplement the steady process towards the decommissioning processend state of Kozloduy units 1 to 4, Ignalina units 1 and 2 and Bohunice V1 units 1 and 2 nuclear power plants, in accordance with their respective decommissioning plans, while keeping the highest level of safety.
2012/10/04
Committee: ITRE
Amendment 102 #

Article 3 – paragraph 1 – subparagraph 2 – point b
(b) EUR [229 629 000] for the Ignalina Programme for the period 2014 to 201720;
2012/10/04
Committee: ITRE
Amendment 122 #

Article 4 – paragraph 1 – point a
(a) Comply with Union's acquis; in particular in the area of nuclear safety the transposition into national law of the Council Directive 2009/71/Euratom on nuclear safety and the Council Directive 2011/70/Euratom on the management of spent fuel and radioactive waste.deleted
2012/10/04
Committee: ITRE
Amendment 157 #

Article 8 – paragraph 1
1. No later than end 20157, an evaluation report shall be established by the Commission on the achievement of the objectives of all the measures, at the level of results and impacts, the efficiency of the use of resources and its Union added value, in view of a decision amending or suspending the measures. The evaluation shall additionally address the scope for simplification, its internal and external coherence, the continued relevance of all objectives. It shall take into account evaluation results on the long-term impact of the predecessor measures.