Renewable Energy, Energy Performance of Buildings and Energy Efficiency Directives: amendments (REPowerEU) (debate)
2022/12/13
Dossiers: 2022/0160(COD)

Shadow opinions (1)

OPINION on the proposal for a directive of the European Parliament and of the Council amending Directive (EU) 2018/2001 on the promotion of the use of energy from renewable sources, Directive 2010/31/EU on the energy performance of buildings and Directive 2012/27/EU on energy efficiency
2022/10/26
Committee: ENVI
Dossiers: 2022/0160(COD)
Documents: PDF(219 KB) DOC(133 KB)
Authors: [{'name': 'Nils TORVALDS', 'mepid': 114268}]

Amendments (9)

Amendment 126 #
Proposal for a directive
Article 1 – paragraph 1 – point 6
Directive (EU) 2018/2001
Article 16 – paragraph 1
(1) The permit-granting process shall cover all relevant administrative permits to build, repower and operate plants for the production of energy from renewable sources, co-located energy storage facilities, as well as assets necessary for their connection to the grid and the assets necessary for the development of the electricity networks required to integrate RES into the system, including grid connection permits and environmental assessments where these are required. The permit-granting process shall comprise all procedures from the acknowledgment of the validity of the application in accordance with paragraph 2 to the notification of the final decision on the outcome of the procedure by the relevant authority or authorities. The provisions of this paragraph, and of Articles 16a and 16b shall also apply to the permit- granting process for network assets necessary for the integration of renewable energy production in the system which are not integrated in the permit-granting process under this paragraph.
2022/09/19
Committee: ENVI
Amendment 136 #
Proposal for a directive
Article 1 – paragraph 1 – point 6
Directive (EU) 2018/2001
Article 16 – paragraph 7
(7) Member States shall ensure that administrative and judicial appeals in the context of a project for the development of renewable energy production plant or its related grid connection and those assets necessary for the development of the electricity networks required to integrate RES into the system, including those related to environmental aspects shall be subject to the most expeditious administrative and judicial procedure that is available at the relevant national, regional and local level.
2022/09/19
Committee: ENVI
Amendment 140 #
Proposal for a directive
Article 1 – paragraph 1 – point 7
Directive (EU) 2018/2001
Article 16a – paragraph 1
(1) Member States shall ensure that the permit-granting process referred to in Article 16(1) shall not exceed one yearsix months for projects in renewables go-to areas. Where duly justified on the ground of extraordinary circumstances, that one-yearsix- months period may be extended by up to three months. In such a case, Member States shall clearly inform the developer about the extraordinary circumstances that justified the extension.
2022/09/19
Committee: ENVI
Amendment 143 #
Proposal for a directive
Article 1 – paragraph 1 – point 7
Directive (EU) 2018/2001
Article 16a – paragraph 2
(2) The permit-granting process for the repowering of plants and for new installations with an electrical capacity of less than 150 kW, co-located energy storage facilities as well as their grid connection, the related transmission and distribution network and the assets necessary for the development of the electricity networks required to integrate RES into the system, located in renewables go-to areas shall not exceed six months. Where duly justified on the ground of extraordinary circumstances, such as on grounds of overriding safety reasons where the repowering project impacts substantially on the grid or the original capacity, size or performance of the installation, that one yearsix month period may be extended by up to three months. Member States shall clearly inform the project developer about the extraordinary circumstances that justify the extension. In the event the repowering project determines an increase in the capacity of the installation and the need for further network developments without increasing the occupied area, the repowering project and the grid development projects associated to the repowering are authorized through the same simplified procedure
2022/09/19
Committee: ENVI
Amendment 148 #
Proposal for a directive
Article 1 – paragraph 1 – point 7
Directive (EU) 2018/2001
Article 16a – paragraph 3 – subparagraph 1
Without prejudice to paragraphs 4 and 5, by derogation from Article 4(2) of Directive 2011/92/EU, Annex I, point 6(b) as far as this concerns the production of renewable hydrogen and Annex II, points 3(a), (b), (d), (h), (i), and 6(c) alone or in conjunction with point 13(a) to that Directive as far as this concerns renewable energy projects, new applications for renewable energy plants, except for biomass combustion plants, including hybrid generation plants that combine different renewable energies and the repowering of plants, in already designated renewables go-to areas for the respective technology, co-located storage facilities as well as their connection to the grid, the related transmission and distribution network, and the related assets necessary for the development of the electricity networks required to integrate RES into the system, shall be exempted from the requirement to carry out a dedicated environmental impact assessment under Article 2(1) of Directive 2011/92/EU, provided that these projects comply with the rules and measures set out in accordance with Article 15c(1), point (b). The exemption from the application of Directive 2011/92/EU above shall not apply to projects which are likely to have significant effects on the environment in another Member State or where a Member State likely to be significantly affected so requests, as provided for in Article 7 of the said Directive.
2022/09/19
Committee: ENVI
Amendment 181 #
Proposal for a directive
Article 1 – paragraph 1 – point 8
Directive (EU) 2018/2001
Article 16b – paragraph 1
(1) Member States shall ensure that the permit-granting process referred to in Article 16(1) shall not exceed twoone years, for projects, including hybrid generation plants that combine different renewable energies, their related transmission and distribution network and storage facilities outside renewables go-to areas. Where duly justified on the grounds of extraordinary circumstances, that twoone-year period may be extended by up to three months. In such a case, Member States shall clearly inform the developer about the extraordinary circumstances that justified the extension.
2022/09/19
Committee: ENVI
Amendment 188 #
Proposal for a directive
Article 1 – paragraph 1 – point 8
Directive (EU) 2018/2001
Article 16b – paragraph 2 – subparagraph 1
Where an environmental assessment is required under Directive 2011/92/EU or Directive 92/43/EEC, it shall be carried out in a single procedure that combines all relevant assessments for a given project. When any such environmental impact assessment is required, the competent authority, taking into account the information provided by the developer, shall issue an opinion on the scope and level of detail of the information to be included by the developer in the environmental impact assessment report, of which the scope shall not be extended subsequently. Where the specific projects have adopted appropriate mitigation measures, any killing or disturbance of the species protected under Article 12(1) of Directive 92/43/EEC and Article 5 of Directive 2009/147/EC shall not be considered deliberate. Where novel mitigation measures to prevent as much as possible the killing or disturbance of species protected under Council Directive 92/43/EEC and Directive 2009/147/EEC, or any other environmental impact, have not been widely tested as regards their effectiveness, Member States may allow their use for one or several pilot projects for a limited time period, provided that the effectiveness of such measures is closely monitored and appropriate steps are taken immediately if they do not prove to be effective. The permit-granting process for the repowering of projects and for new installations with an electrical capacity of less than 150 kW, co-located storage facilities as well as their grid connection, located outside renewables go-to areas shall not exceed one yearsix months including environmental assessments where required by relevant legislation. Where duly justified on the ground of extraordinary circumstances, this one-yearsix-months period may be extended by up to three months. Member States shall clearly inform the developers about the extraordinary circumstances that justified the extension.
2022/09/19
Committee: ENVI
Amendment 191 #
Proposal for a directive
Article 1 – paragraph 1 – point 8
Directive (EU) 2018/2001
Article 16b – paragraph 2 – subparagraph 2
Member States shall facilitate the repowering of projects located outside go- to areas by ensuring that, if an environmental assessment for a project is required under the Union environmental legislation, such assessment shall be limited to the potential impacts stemming from the change or extension compared to the original project. In the event the repowering project determines an increase in the capacity of the installation and the need for further network developments without increasing the occupied area, the repowering project and the grid development projects associated to the repowering are authorized through the same simplified procedure.
2022/09/19
Committee: ENVI
Amendment 203 #
Proposal for a directive
Article 1 – paragraph 1 – point 9
Directive (EU) 2018/2001
Article 16c – paragraph 1 a (new)
(1a) In order to facilitate the deployment of rooftop solar, Member shall ensure that the installation of building-integrated solar is exempted from environmental impact assessment under Article 2(1) of Directive 2011/92/EU and from building permitting.
2022/09/19
Committee: ENVI