72 Amendments of Andreas GLÜCK related to 2023/0081(COD)

Amendment 62 #
Proposal for a regulation
Recital 10
(10) To achieve the 2030 objectives a particular focus is needed on some of the net-zero technologies, also in view their significant contribution towards the path to net zero by 2050. These technologies include solar photovoltaic and solar thermal technologies, onshore and offshore renewable technologies, battery/storage technologies, heat pumps and geothermal energy technologies, electrolysers and fuel cells, sustainable biofuels including sustainable biogas/biomethane, carbon capture and storage technologies and grid technologies. These technologies play a key role in the Union’s open strategic autonomy, ensuring that citizens have access to clean, affordable, secure energy. Given their role, these technologies should benefit from even faster permitting procedures, obtain the status of the highest national significance possible under national law and benefit from additional support to crowd-in investments.
2023/06/15
Committee: ENVI
Amendment 73 #
Proposal for a regulation
Recital 13
(13) The development of carbon capture and storage solutions for industry is confronted with a coordination failure. On the one hand, despite the growing CO2 price incentive provided by the EU Emissions Trading System, for industry to invest into capturing CO2 emissions making such investments economically viable, they face a significant risk of not being able to access a permitted geological storage site. On the other hand, investors into first CO2 storage sites face upfront costs to identify develop and appraise them even before they can apply for a regulatory storage permit. Transparency about potential CO2 storage capacity in terms of the geological suitability of relevant areas and existing geological data, in particular from the exploration of hydrocarbon production sites, can support market operators to plan their investments. Member State should make such data publicly available and report regularly in a forward-looking perspective about progress in developing CO2 storage sites and the corresponding needs for injection and storage capacities above, in order to collectively reach the Union-wide target for CO2 injection capacity. To ensure that injection capacity will deliver the expected CO2 removals and to avoid stranded assets, CCS value chains including capture-transport and storage need to be established by 2030.
2023/06/15
Committee: ENVI
Amendment 82 #
Proposal for a regulation
Recital 14 a (new)
(14a) To reach the Union’s target of 60 million tonnes of annual operational CO2 injection capacity by 2030 it is necessary to support cross-border transportation of CO2 and to overcome the limitations set by the London Protocol. The Commission should develop a CO2 infrastructure plan with actions towards creating a regulatory and financial framework to establish a unified CCS market in the EU.
2023/06/15
Committee: ENVI
Amendment 124 #
Proposal for a regulation
Recital 5
(5) The higher energy prices after the unjustified and unlawful military aggression by the Russian Federation against Ukraine, gave a strong impetus to accelerate the implementation of the European Green Deal and reinforce the resilience of the Energy Union by speeding up the clean energy transition and ending any dependence on fossil fuels exported from the Russian Federation. The REPowerEU plan35 plays a key role in responding to the hardships and global energy market disruption caused by the invasion of Ukraine by the Russian Federation. That plan aims to accelerate the energy transition in the European Union, in order to reduce the Union’s gas and electricity consumption and to boost investments in the deployment of energy efficient and low carbon solutions. That plan sets inter alia the targets to double solar photovoltaic capacity by 2025 and to install 600 GW of solar photovoltaic capacity by 2030; to double the rate of deployment of heat pumps; to produce 10 million tonnes of domestic renewable hydrogen by 2030; and to substantially increase production of biomethane up to 35 bcm by 2030. The plan also sets out that achieving the REPowerEU goals will require diversifying the supply of low carbon energy equipment and of critical raw materials, reducing sectoral dependencies, overcoming supply chain bottlenecks and expanding the Union’s clean energy technology manufacturing capacity. As part of its efforts to increase the share of renewable energy in power generation, industry, buildings and transport, the Commission proposes to increase the target in the Renewable Energy Directive to 45% by 2030 and to increase the target in the Energy Efficiency Directive to 13%. This would bring the total renewable energy generation capacities to 1236 GW by 2030, in comparison to 1067 GW by 2030 envisaged under the 2021 proposal and will see increased needs for storage through batteries to deal with intermittency in the electricity grid. Similarly, policies related to the decarbonisation of the road sector, such as Regulation (EU) 2019/631 and Regulation (EU) 2019/1242 will be strong drivers for a further electrification of the road transport sector and thus increasing demand for batteries. _________________ 35 Communication of 18 May 2022 from the Commission to the European Parliament, the European Council, the Council, the European Economic and Social Committee and the Committee of the Regions, REPowerEU Plan, COM/2022/230 final, 18.05.2022.
2023/06/23
Committee: ITRE
Amendment 142 #
Proposal for a regulation
Recital 7
(7) To meet the 2030 and 2050 climate and energy targets, energy efficiency needs to be prioritised. Saving energy is the cheapest, safest and cleanest way to meet those targets. ‘Energy efficiency first’ is an overall principle of EU energy policy and is important in both its practical applications in policy and investment decisions. Therefore, it is essential to expand the Union’s manufacturing capacity for energy efficient technologies, such as heat pumps and smart grid technologies, that help the EU reduce and control its energy consumption.
2023/06/23
Committee: ITRE
Amendment 149 #
Proposal for a regulation
Recital 8
(8) The Union’s decarbonisation objectives, security of energy supply, digitalisation of the energy system and electrification of demand, for example in mobility and the need for fast recharging points, require an enormous expansion of electricity grids in the European Union, both at transmission level and at distribution level. At transmission level, high-voltage direct current (HVDC) systems are needed to connect offshore renewable energies; while at distribution level, connecting electricity providers and managing demand-side flexibility builds on investments in innovative grid technologies, such as electric vehicles smart charging (EVSC), energy efficiency building and industry automation and smart controls, advanced meter infrastructure (AMI) and home energy management systems (HEMS). The electricity grid needs to interact with many actors or devices based on a detailed level of observability, and hence availability of data, to enable flexibility, smart charging and smart buildings with smart electricity grids and small scale flexibility services enabling demand side response from consumers and the uptake of renewables. Connecting the net-zero technologies to the network of the European Union requires the substantial expansion of manufacturing capabilities for electricity grids in areas such as offshore and onshore cables, substations and transformers.
2023/06/23
Committee: ITRE
Amendment 151 #
Proposal for a regulation
Recital 8 a (new)
(8a) Renewable, biobased energy resources have the potential to replace fossil energy resources and critical raw materials. These resources are derived from biological materials, which can be replenished naturally. In addition, they emit less greenhouse gas emissions, reduce the dependence on imported fossil fuels, support rural development and create jobs in rural areas and decrease waste and pollution by utilizing agricultural and forestry residues. Additionally, renewable resources lessen our reliance on critical raw materials that are becoming scarce.
2023/06/23
Committee: ITRE
Amendment 154 #
Proposal for a regulation
Recital 9
(9) Additional policy effort is necessary to support those technologies that are commercially available and have a good potential for rapid scale up to support the Union’s 2030 and 2050 climate targets, improve the security of supply for net-zero technologies and their supply chains, and safeguard or strengthen the overall resilience and competitiveness of the Union’s energy system. It includes access to a safe and sustainable source of best in class fuels, as described in recital 8 of Commission Delegated Regulation (EU) 2022/1214.
2023/06/23
Committee: ITRE
Amendment 176 #
Proposal for a regulation
Recital 12
(12) In 2020 the European Commission adopted an EU strategy for energy system integration. It set out a vision on how to accelerate the transition towards a more integrated energy system, one that supports a climate neutral economy at the least cost across sectors. It encompasses three complementary and mutually reinforcing concepts: first, a more ‘circular’ energy system, with energy efficiency at its core; second, a greater direct electrification of end-use sectors; third, the use of renewable and low-carbon fuels, including hydrogen, for end-use applications where direct heating or electrification are not feasible, not efficient or have higher costs. Considerations related to energy system integration refer to solutions for fully integrating all the electricity generated by renewable energy installations into the wider energy system. This means, for instance, adopting technical solutions that allow for the integration of surplus electricity generated by renewable electricity installations, including through storage in its various forms and demand- side management.
2023/06/23
Committee: ITRE
Amendment 179 #
Proposal for a regulation
Recital 62
(62) Net-zero regulatory sandboxes can be an important tool to promote innovation in the field of net-zero technologies ands well as regulatory learning and should include all technologies with potential to enable the transition to a climate neutral, clean economy and reduce strategic dependencies. Innovation needs to be enabled through experimentation spaces as scientific outcomes need to be tested in a controlled real-word environment. Regulatory sandboxes should be introduced to test innovative net-zero technologies in a controlled environment for a limited amount of time It is appropriate to strike a balance between legal certainty for participants in the Net- Zero regulatory sandboxes and the achievement of the objectives of Union law. As Net-Zero regulatory sandboxes must in any case comply with the essential requirements on Net-Zero technology laid out in Union and national law, it is appropriate to provide that participants , who comply with the eligibility requirements for Net-Zero regulatory sandboxes and who follow, in good faith, the guidance provided by the competent authorities and the terms and conditions of the plan agreed with those authorities, are not subject to any administrative fines or penalties. This is justified as the safeguards in place will, in principle, ensure effective compliance with Union or Member State law on the Net-Zero technology supervised in the regulatory sandboxes. The Commission will publish a Guidance for Sandboxes document in 2023 as announced in the New European Innovation Agenda to support Member States in preparing the net zero technology sandboxes. Those innovative technologies could eventually be essential to achieve the Union’s climate neutrality objective, ensure the security of supply and resilience of the Union’s energy system, and consequently enter the scope of strategic net-zero technologies.
2023/06/15
Committee: ENVI
Amendment 209 #
Proposal for a regulation
Article 1 – paragraph 2 b (new)
2b. The yearly review and update of the list of net-zero technologies and the annex of strategic net-zero technologies shall be based on the following criteria and an assessment of: 1. Technology neutrality with the aim of including relevant technologies that meet the criteria for substantial contribution to climate change mitigation in accordance with article 10 of Regulation (EU) 2020/852; 2. Technology that is critical for meeting EU's climate neutrality target; 3. Technology with an untapped potential as well as technologies facing market failures due to insufficient funding and regulation;
2023/06/15
Committee: ENVI
Amendment 217 #
Proposal for a regulation
Recital 17
(17) To address security of supply issues and contribute to supporting the resilience of Union’s energy system and decarbonisation and modernisation efforts, the net-zero technology manufacturing capacity in the Union needs to expand. Union manufacturers of solar photovoltaic (PV) technologies need to increase their competitive edge and improve security of supply perspectives, by aiming to reach at least 30 gigawatt of operational solar PV manufacturing capacity by 2030 across the full PV value chain, in line with the goals set out in the European Solar Photovoltaic Industry Alliance, which is supported under the Union’s Solar Energy Strategy.38 Union manufacturers of wind and heat pump technologies need to consolidate their competitive edge and maintain or expand their current market shares throughout this decade, in line with the Union’s technology deployment projections that meet its 2030 energy and climate targets.39 This translates into a Union manufacturing capacity for wind of at least 36 GW and, respectively, for heat pumps of at least 31 GW in 2030. Union manufacturers of batteries and electrolysers need to consolidate their technology leadership and actively contribute to shaping these markets. For battery technologies this would mean contributing to the objectives of the European Battery Alliance and aim at almost 90% of the Union’s battery annual demand being met by the Union’s battery manufacturers, translating into a Union manufacturing capacity of at least 550 GWh in 2030. For EU electrolyser manufacturers, the REPowerEU plan projects 10 million tonnes of domestic renewable hydrogen production and a further up to 10 million tonnes of renewable hydrogen imports by 2030. To ensure EU’s technological leadership translates into commercial leadership, as supported under the Electrolyser Joint Declaration of the Commission and the European Clean Hydrogen Alliance, EU electrolyser manufacturers should further boost their capacity, such that the overall installed electrolyser capacity being deployed reaches at least 100 GW hydrogen by 2030. Furthermore, the RePowerEU Plan sets an objective of boosting biomethane production to 35 bcm by 2030. Biomethane, with its supply chain largely based in Europe today, already contributes to Europe’s resilience—a contribution that should be further promoted. _________________ 38 Communication from the Commission to the European Parliament, the Council, the European Economic and Social Committee and the Committee of the Regions: EU Solar Energy Strategy, SWD(2022) 148 final, 18.05.2022. 39 As per REPowerEU objectives set out in the REPowerEU Plan, COM/2022/230 final, and accompanying Commission Staff Working Document Implementing the Repower EU Action Plan: Investment Needs, Hydrogen Accelerator and achieving the Bio-Methane Targets Accompanying the Document : Communication from the Commission to the European Parliament, the European Council, the Council, the European Economic and Social Committee and the Committee of the Regions REPowerEU Plan, SWD/2022/230 final, 18.05.2022
2023/06/23
Committee: ITRE
Amendment 237 #
Proposal for a regulation
Recital 21
(21) In order to maintain competitiveness and reduce current strategic import dependencies in key net- zero technology products and their supply chains, while avoiding the formation of new ones, the Union needs to continue strengthening its net zero industrial base and become more competitive and innovation friendly. The Union needs to enable the development of manufacturing capacity faster, simpler and in a more predictable way and to reduce administrative burden and level the playing field with international competitors.
2023/06/23
Committee: ITRE
Amendment 240 #
Proposal for a regulation
Article 3 – paragraph 1 – point c
(c) ‘innovative net-zero technologies’ means technologies which satisfy the definition of ‘net-zero technologies’, except that they have not reached a tith potential to enable the transition to a climate neutral, clean echonology readiness level of at least 8my and reduce strategic dependencies, and that comprise genuine innovation which are not currently available on the market and are advanced enough to be tested in a controlled environment.
2023/06/15
Committee: ENVI
Amendment 247 #
Proposal for a regulation
Recital 23
(23) In addition, the Communication on the Green Deal Industrial Plan for the Net- Zero Age42 sets out a comprehensive approach to support a clean energy technology scale up based on four pillars. The first pillar aims at creating a regulatory environment that simplifies and fast-tracks permitting for new net-zero technology manufacturing and assembly sites and facilitates the scaling up of the net-zero industry of the Union. The second pillar of the plan is to boost investment in and financing of net-zero technology production, through the revised Temporary Crisis and Transition Framework adopted in March 2023 and the creation of a European Sovereignty fund to preserve the European edge on critical and emerging technologies relevant to the green and digital transitions. The third pillar relates to developing the skills needed to make the transition happen and increase the number of skilled workers in the clean energy technology sector. The fourth pillar focuses on trade and the diversification of the supply chain of critical raw materials. That includes creating a critical raw materials club, working with like-minded partners to collectively strengthen supply chains and diversifying away from single suppliers for critical input. _________________ 42 Communication from the Commission to the European Parliament, the European Council, the Council, the European Economic and Social Committee and the Committee of the Regions: A Green Deal Industrial Plan for the Net-Zero Age, COM/2023/62 final, 01.02.2023.
2023/06/23
Committee: ITRE
Amendment 248 #
Proposal for a regulation
Recital 23
(23) In addition, the Communication on the Green Deal Industrial Plan for the Net- Zero Age42 sets out a comprehensive approach to support a clean energy technology scale up based on four pillars. The first pillar aims at creating a regulatory environment that simplifies and fast-tracks permitting for new net-zero technology manufacturing and assembly sites and facilitates the scaling up of the net-zero industry of the Union. The second pillar of the plan is to boost investment in and financing of net-zero technology production, through the revised Temporary Crisis and Transition Framework adopted in March 2023 and the creation of a European Sovereignty fund to preserve the European edge on critical and emerging technologies relevant to the green and digital transitions. The third pillar relates to developing the skills needed to make the transition happen and increase the number of skilled workers in the clean energy technology sector. The fourth pillar focuses on trade and the diversification of the supply chain of critical raw materials. That includes creating a critical raw materials club, working with like-minded partners to collectively strengthen supply chains and diversifying away from single suppliers for critical input. _________________ 42 Communication from the Commission to the European Parliament, the European Council, the Council, the European Economic and Social Committee and the Committee of the Regions: A Green Deal Industrial Plan for the Net-Zero Age, COM/2023/62 final, 01.02.2023.
2023/06/23
Committee: ITRE
Amendment 318 #
Proposal for a regulation
Article 7 – paragraph 1
1. Where an environmental impact assessment must be carried out in accordance with Articles 5 to 9 of Directive 2011/92/EU, the project promoter concerned shall request an opinion to the competent authority referred to in Article 4 on the scope and level of detail of the information to be included in the environmental impact assessment report pursuant to Article 5(1) of that Directive. The national competent authority shall ensure that the opinion referred to in the first subparagraph is issued as soon as possible and within a period of time not exceeding 3015 days from the date on which the project promoter submitted its request.
2023/06/15
Committee: ENVI
Amendment 324 #
Proposal for a regulation
Recital 46
(46) The Innovation Fund also provides a very promising and cost efficient avenue to support the scaling up of manufacturing and deployment of renewableclean hydrogen and other strategic net zero technologies in Europe, thus reinforcing Europe’s sovereignty in key technologies for climate action and energy security.
2023/06/23
Committee: ITRE
Amendment 327 #
Proposal for a regulation
Recital 47
(47) A European Sovereignty Fund would provide a structural answer to the investment needs. It will help preserving a European edge on critical and emerging technologies relevant to the green and digital transitions, including net-zero technologies. This structural instrument will build on experience of coordinated multi-country projects under the IPCEIs and seek to enhance all Member States’ access to such projects, thereby safeguarding cohesion and the Single Market against risks caused by unequal availability of State Aids.deleted
2023/06/23
Committee: ITRE
Amendment 328 #
Proposal for a regulation
Recital 47
(47) A European Sovereignty Fund would provide a structural answer to the investment needs. It will help preserving a European edge on critical and emerging technologies relevant to the green and digital transitions, including net-zero technologies. This structural instrument will build on experience of coordinated multi-country projects under the IPCEIs and seek to enhance all Member States’ access to such projects, thereby safeguarding cohesion and the Single Market against risks caused by unequal availability of State Aids.deleted
2023/06/23
Committee: ITRE
Amendment 334 #
Proposal for a regulation
Article 7 – paragraph 3
3. The national competent authority shall ensure that the authorities concerned issue a reasoned conclusion as referred to in Article 1(2), point (g)(iv) of Directive 2011/92/EU on the environmental impact assessment within threewo months of receiving all necessary information gathered pursuant to Articles 5, 6 and 7 of that Directive and completing the consultations referred to in Articles 6 and 7 of that Directive.
2023/06/15
Committee: ENVI
Amendment 338 #
Proposal for a regulation
Article 7 – paragraph 3 b (new)
3b. The lack of a reasoned conclusion by the competent authority within the applicable time limits referred to in paragraph 3 shall result in a positive conclusion of the assessment procedure.
2023/06/15
Committee: ENVI
Amendment 340 #
Proposal for a regulation
Article 7 – paragraph 4
4. The timeframes for consulting the public concerned on the environmental report referred to in Article 5(1) of Directive 2011/92/EU shall not be longer than 45 days. In cases falling under the second sub-paragraph of Article 6(4), this period shallcan be extended to 90 daysmaximum 90 days. In that event, the national competent authority shall inform the project promoter of the reasons justifying the extension.
2023/06/15
Committee: ENVI
Amendment 372 #
Proposal for a regulation
Recital 55
(55) Net-zero technology manufacturing projects undergo lengthy and complex permitting procedures of 2-7 years, depending on the Member State, technology and value chain segment. Considering the size of required investments – in particular for gigafactory- size projects which are needed to reach the expected economies of scale – inadequate permitting creates an additional and often detrimental barrier to increase net-zero technology manufacturing capacity in the Union. In order to provide project promoters and other investors with the security and clarity needed to increase development of net-zero technologies manufacturing projects, Member States should ensure that the permit-granting process related to such projects does not exceed pre-set time limits. For Net Zero Strategic Projects the length of the permit- granting process should not exceed twelve9 months for facilities with a yearly production output of more than 1 GW, and 96 months for those with a yearly production output of less than 1 GW. For all other net-zero technology manufacturing projects, the length of the permit-granting process should not exceed eighteen12 months for facilities with a yearly production output of more than 1 GW, and twelve9 months for those with a yearly production output of less than 1 GW. For net-zero technologies for which the GW metric is not relevant, such as grids and carbon capture and storage (CCS) or carbon capture and usage (CCU) technologies, the upper limits of the aforementioned deadlines should apply. For the expansion of existing production lines, each of the aforementioned time limits should be halved.
2023/06/23
Committee: ITRE
Amendment 374 #
Proposal for a regulation
Article 8 – paragraph 2
2. Where plans include provisions for the development of net-zero technology manufacturing projects, including net-zero strategic projects and all the necessary infrastructure, are subject to an assessment pursuant to Directive 2001/42/EC and pursuant to Article 6 of Directive 92/43/EEC, those assessments shall be combined. Where relevant, that combined assessment shall also address the impact on potentially affected water bodies and verify whether the plan potentially prevent a water body from achieving good status or good potential or cause deterioration of status or of potential referred to in Article 4 of Directive 2000/60/EC or would potentially hamper that a water body achieves good status or good potential. Where relevant Member States are required to assess the impacts of existing and future activities on the marine environment, including land-sea interactions, as referred to in Article 4 of Directive 2014/89/EU, these impacts shall also be covered by the combined assessment. When there is a need for an assessment according to this Article these assessments shall be conducted in such a way that they do not lead to a prolongation of the time limits referred to in Article 13(1) and 13(2).
2023/06/15
Committee: ENVI
Amendment 423 #
Proposal for a regulation
Article 1 – paragraph 2 – introductory part
2. To achieve the general objective referred to in paragraph 1, this Regulation contains measures with a view to ensuring:the aim
2023/06/23
Committee: ITRE
Amendment 459 #
Proposal for a regulation
Article 1 – paragraph 3 a (new)
3a. The value chains created and strengthened as a result of this Regulation both in the Union and in third countries shall be further strengthened after 2030. The Commission shall take this into account when conducting the review referred to in Article 35.
2023/06/23
Committee: ITRE
Amendment 461 #
Proposal for a regulation
Article 12 – paragraph 3
3. Net-zero strategic projects shall be considered to contribute to the security of supply of strategic net-zero technologies in the Union and therefore to be in the public interest. With regard to the environmental impacts addressed in Articles 6(4) and 16(1)I of Directive 92/43/EEC, Article 4(7) of Directive 2000/60/EC and Article 9(1)(a) of Directive 2009/147/EC, net-zero strategic projects in the Union shall, until climate neutrality is achieved, be considered as being of public interest and may be considershall be presumed as havbeing ain the overriding public interest provided that all the conditions set out in those Directives are fulfilled.
2023/06/15
Committee: ENVI
Amendment 468 #
Proposal for a regulation
Article 2 – paragraph 1
This Regulation applies to net-zero technologies and their value chains, including important input materials produced using low-carbon energy, except for Articles 26 and 27 of this Regulation, which apply to innovative net-zero technologies. Raw materials processed materials or components falling under the scope of Regulation (EU) …/… [add footnote with publication references of the Critical Raw Materials Regulation] shall be excluded from the scope of this Regulation.
2023/06/23
Committee: ITRE
Amendment 470 #
Proposal for a regulation
Article 2 – paragraph 1
This Regulation applies to net-zero technologies, except for Articles 26 and 27 of this Regulaincluding their essential components, materials and machinery that are indispensable to their production and functioning, which apply to innovative net-zero technologies. Raw materials processed materials or components falling under the scope of Regulation (EU) …/… [add footnote with publication references of the Critical Raw Materials Regulation] shall be excluded from the scope of this Regulation.
2023/06/23
Committee: ITRE
Amendment 487 #
Proposal for a regulation
Article 13 – paragraph 4
4. National competent authorities shall ensure that the lack of reply of the relevant administrative bodies within the applicable time limits referred to in this Article results in the specific intermediary steps to be considered as approved, except where the specific project is subject to an environmental impact assessment pursuant to Council Directive 92/43/EEC or Directive 2000/60/EC, Directive 2008/98/EC, Directive 2009/147/EC, Directive 2010/75/EU, 2011/92/EU or Directive 2012/18/EU or a determination of whether such environmental impact assessment is necessary and the relevant assessments concerned have not yet been carried out, or where the principle of administrative tacit approval does not exist in the national legal system. The need for such an impact assessment shall be decided on and communicated to the project promoter within 14 days. When this is not done within this time limit it shall be considered that such an impact assessment is not needed. This provision shall not apply to final decisions on the outcome of the process, which are to be explicit. All decisions shall be made publicly available.
2023/06/15
Committee: ENVI
Amendment 495 #
Proposal for a regulation
Article 3 – paragraph 1 – point a
(a) ‘net-zero technologies’ means renewable energy technologies66 ; electricity and heat storage technologies; heat pumps; grid technologies; renewable fuels of non-biological origin technologies, including the relevant transport infrastructure; sustainable alternative fuels technologies67 ; electrolysers and fuel cells; liquid hydrogen technologies; advanced technologies to produce energy from nuclear processes with minimal waste from the fuel cycle, small modular reactors, and related best-in-class fuels; carbon capture, utilisation, and storage technologies, including the relevant transport infrastructure; and energy-system related energy efficiency technologies. They refer to the final products, specific components and specific machinery primarily used for the production of those products. They shall have reached a technology readiness level of at least 8 along the value chain. _________________ 66 ‘renewable energy' means ‘renewable energy’ as defined in Directive (EU) 2018/2001 of the European Parliament and of the Council of 11 December 2018 on the promotion of the use of energy from renewable sources 67 ‘sustainable alternative fuels’ means fuels covered by the Proposal for a Regulation of the European Parliament and of the Council on ensuring a level playing field for sustainable air transport, COM/2021/561 final and by the Proposal for a Regulation of the European Parliament and Council on the use of renewable and low-carbon fuels in maritime transport COM/2021/562 final.
2023/06/23
Committee: ITRE
Amendment 496 #
Proposal for a regulation
Article 3 – paragraph 1 – point a
(a) ‘net-zero technologies’ means renewable energy technologies66 ; electricity and heat storage technologies; heat pumps; grid technologies; renewable fuels of non-biological origin technologies; sustainable alternative fuels technologies67 ; electrolysers and fuel cells; advanced technologies to produce energy from nuclear processes with minimal waste from the fuel cycle, small modular reactors, and related best-in-class fuels; carbon capture, utilisation, and storage technologies; and energy-system related energy efficiency and renewable bioenergy technologies. They refer to the final products, specific components and specific machinery, including technologies for circularity, primarily used for the production of those products. They shall have reached a technology readiness level of at least 8. _________________ 66 ‘renewable energy' means ‘renewable energy’ as defined in Directive (EU) 2018/2001 of the European Parliament and of the Council of 11 December 2018 on the promotion of the use of energy from renewable sources 67 ‘sustainable alternative fuels’ means fuels covered by the Proposal for a Regulation of the European Parliament and of the Council on ensuring a level playing field for sustainable air transport, COM/2021/561 final and by the Proposal for a Regulation of the European Parliament and Council on the use of renewable and low-carbon fuels in maritime transport COM/2021/562 final.
2023/06/23
Committee: ITRE
Amendment 517 #
Proposal for a regulation
Article 3 – paragraph 1 – point a a (new)
(aa) ‘sustainable alternative fuels’ means fuels covered by Directive (EU) 2018/2001 of the European Parliament and of the Council of 11 December 2018 on the promotion of the use of energy from renewable sources.
2023/06/23
Committee: ITRE
Amendment 523 #
Proposal for a regulation
Article 3 – paragraph 1 – point b
(b) ‘component’ means a small parnufactured element of a net-zero technology that is manufactured and traded by a company starting from processed materials;
2023/06/23
Committee: ITRE
Amendment 607 #
Proposal for a regulation
Article 4 – paragraph 1
1. By …[3 months after the date of entry into force of this Regulation], Member States shall designate one national competent authority which shall be responsible for facilitating and coordinating and streamlining the permit- granting process for net-zero technology manufacturing projects, including for net- zero strategic projects, and to provide advice on reducing administrative burden in line with Article 5.
2023/06/23
Committee: ITRE
Amendment 612 #
Proposal for a regulation
Article 4 – paragraph 2
2. The national competent authority referred to in paragraph 1 shall be the sole point of contact for the project promoter in the permit-granting process leading to a comprehensive decision for a given project and shall coordinate the submission of all relevant documents and information. A case officer shall be assigned by the One Stop Shops to net-zero technology manufacturing that have been granted the status of Strategic Project. The case officer shall provide an easy point of contact and assist the Project Promoter in navigating any internal bureaucracy.
2023/06/23
Committee: ITRE
Amendment 628 #
Proposal for a regulation
Article 4 – paragraph 3 – point c a (new)
(ca) the national competent authority referred to in paragraph 1 ensures that no delays result from the delegation of tasks.
2023/06/23
Committee: ITRE
Amendment 646 #
Proposal for a regulation
Article 4 – paragraph 7
7. Member States shall ensure that the national competent authority responsible for the entire permit-granting processes or any authority to which tasks are delegated pursuant to paragraph 3, including all procedural steps, has a sufficient number of qualified staff and sufficient financial, technical and technological resources necessary, including for up- and re-skilling, for the effective performance of its tasks under this Regulation. If Member States do not have the resources to fulfil the requirements set out in this paragraph, the Commission shall assist them with resources aiding the member state in fulfilling those requirements.
2023/06/23
Committee: ITRE
Amendment 676 #
Proposal for a regulation
Article 6 – paragraph 1 – introductory part
1. The permit-granting process for net-zero technology manufacturing projects shall not exceed any of the following time limit12 months:
2023/06/23
Committee: ITRE
Amendment 680 #
Proposal for a regulation
Article 6 – paragraph 1 – point a
(a) 12 months for the construction of net-zero technology manufacturing projects with a yearly manufacturing capacity of less than 1 GW;deleted
2023/06/23
Committee: ITRE
Amendment 687 #
Proposal for a regulation
Article 6 – paragraph 1 – point b
(b) 18 months for the construction of net-zero technology manufacturing projects, with a yearly manufacturing capacity of more than 1 GW.deleted
2023/06/23
Committee: ITRE
Amendment 699 #
Proposal for a regulation
Article 6 – paragraph 2
2. For net-zero technology manufacturing projects for which a yearly manufacturing capacity is not measured in GW, the permit-granting process shall not exceed a time limit of 182 months.
2023/06/23
Committee: ITRE
Amendment 714 #
Proposal for a regulation
Article 6 – paragraph 6
6. No later than one month following the receipt of the permit-granting application, competent authorities shall validate the application or, if the project promoter has not sent all the information required to process an application, request the project promoter to submit a complete application within fourteenthirty days from that request, outlining which information is missing. The date of the acknowledgement of the validity of the application by the national competent authority referred to in Article 4(1) shall serve as the start of the permit granting process.
2023/06/23
Committee: ITRE
Amendment 721 #
Proposal for a regulation
Article 6 – paragraph 9 a (new)
9a. In accordance with this Regulation, the European Commission shall adopt guidelines to define a minimum set of permit-granting requirements that Member States must adhere to for net-zero technology manufacturing projects, in particular to simplify the preparatory work for promoters submitting manufacturing projects, while facilitating the instruction of requests by administrations.
2023/06/23
Committee: ITRE
Amendment 725 #
Proposal for a regulation
Article 6 – paragraph 9 b (new)
9b. National competent authorities shall ensure that the lack of reply of the relevant administrative bodies within the applicable time limits referred to in this Article results in the specific intermediary steps to be considered as approved, except where the principle of administrative tacit approval does not exist in the national legal system. This provision shall also apply to final decisions on the outcome of the process and for these decisions an explicit notice of tacit approval shall be send to the project promoter within a week after the tacit approval came into effect. All decisions, including a notice of tacit approval, shall be made publicly available.
2023/06/23
Committee: ITRE
Amendment 735 #
Proposal for a regulation
Annex – row 6
6. Sustainable biofuels including biogas/biomethane technologies
2023/06/22
Committee: ENVI
Amendment 750 #
Proposal for a regulation
Article 8 – paragraph 1
1. When preparing plans, including zoning, spatial plans and land use plans, national, regional and local authorities shall, where appropriate, include in those plans provisions for the development of net-zero technology manufacturing projects, including net-zero strategic projects and the relevant infrastructure. Priority shall be given to artificial and built surfaces, industrial sites, brownfield sites, and, where appropriate, greenfield sites not usable for agriculture and forestry.
2023/06/23
Committee: ITRE
Amendment 880 #
Proposal for a regulation
Article 11 – paragraph 6
6. Where the Commission or a Member State finds that a net-zero strategic project has undergone substantial changes or that it no longer fulfils the criteria set out in Article 10(1) or 10(3), or where its recognition was based on an application containing incorrecfraudulent information, it shall inform the project promoter concerned. After hearing the project promoter, the Member State may repeal the decision granting a project the status of net-zero strategic project.
2023/06/23
Committee: ITRE
Amendment 889 #
Proposal for a regulation
Article 12 – paragraph 1
1. Project promoters and all authorities that, under national law, are competent to issue various permits and authorisations related to the planning, design and construction of immovable assets, including energy infrastructure, shall ensure that for net-zero strategic projects those processes, including contact between project promoter and any authority before the application is officially submitted and complete, are treated in the most rapid way possible in accordance with Union and national law.
2023/06/23
Committee: ITRE
Amendment 912 #
Proposal for a regulation
Article 13 – paragraph 1 – introductory part
1. The permit-granting process for net-zero strategic projects shall not exceed any of the following time limit9 months:
2023/06/23
Committee: ITRE
Amendment 914 #
Proposal for a regulation
Article 13 – paragraph 1 – point a
(a) 9 months for the construction of net-zero strategic projects with a yearly manufacturing capacity of less than 1 GW;deleted
2023/06/23
Committee: ITRE
Amendment 919 #
Proposal for a regulation
Article 13 – paragraph 1 – point b
(b) 12 months for the construction of net-zero strategic projects, with a yearly manufacturing capacity of more than 1 GW;deleted
2023/06/23
Committee: ITRE
Amendment 924 #
Proposal for a regulation
Article 13 – paragraph 1 – point c
(c) 18 months for all necessary permits to operate a storage site in accordance with Directive 2009/31/EC.deleted
2023/06/23
Committee: ITRE
Amendment 926 #
Proposal for a regulation
Article 13 – paragraph 2
2. For net-zero strategic technologies for which a yearly manufacturing capacity is not measured in GW, the permit-granting process shall not exceed a time limit of 129 months.
2023/06/23
Committee: ITRE
Amendment 945 #
Proposal for a regulation
Article 14 – paragraph 1
1. The Commission and the Member States shall undertake activities to accelerate and crowd-in private investments in net-zero strategic projects. Such activities may, without prejudice to Article 107 and Article 108 of the TFEU, include providing and coordinating administrative support to net-zero strategic projects facing difficulties in accessing finance.
2023/06/23
Committee: ITRE
Amendment 949 #
Proposal for a regulation
Article 14 – paragraph 2 – introductory part
2. The Commission and Member States may provide administrative and operational support to net-zero strategic projects to facilitate their rapid and effective implementation, including by providing:
2023/06/23
Committee: ITRE
Amendment 951 #
Proposal for a regulation
Article 14 – paragraph 2 – introductory part
2. Member States and the Commission shall may provide administrative support to net-zero strategic projects to facilitate their rapid and effective implementation, including by providing:
2023/06/23
Committee: ITRE
Amendment 973 #
Proposal for a regulation
Article 15 – paragraph 1
1. The Net-Zero Europe Platform as established in Article 28 shall discuss financial needs and bottlenecks of net-zero strategic projects, potential best practices, in particular to develop EU cross-border supply chains, notably based on regular exchanges with the relevant industrial alliances, including alliances representing SMEs.
2023/06/23
Committee: ITRE
Amendment 1327 #
Proposal for a regulation
Article 23 – paragraph 1 – point c a (new)
(ca) Make use of the best practices already in use in the member states, especially with regard to regional continuing education or additional training.
2023/06/23
Committee: ITRE
Amendment 1347 #
Proposal for a regulation
Article 25 – paragraph 1 – point 6
(6) promote adequate working conditions in jobs in net-zero technology industries, the activation of youth, women and seniors to the labour market for net- zero technology industries, and the attraction of skilled workers from third countries, and thereby achieve a more diverse workforce;deleted
2023/06/23
Committee: ITRE
Amendment 1362 #
Proposal for a regulation
Article 26 – paragraph 2 – introductory part
2. The modalities and the conditions for the establishment and operation of the net-zero regulatory sandboxes under this Regulation shall be adopted through implementing acts in accordance with the examination procedure referred to in Article 36. The modalities and conditions shall to the extent possible support flexibility for national competent authorities to establish and operate their Net-zero regulatory sandboxes, foster innovation and regulatory learning and shall particularly take into account the special circumstances and capacities of participating SMEs, including start-ups; allow the establishing of regulatory sandboxes in co-operation with universities and research facilities and use existing facilities as regulatory sandboxes where deliberate. The implementing acts referred to in paragraph 3 shall include common main principles on the following issues:
2023/06/23
Committee: ITRE
Amendment 1389 #
Proposal for a regulation
Article 27 – paragraph 1 – point c a (new)
(ca) Member states can establish without limitations set by the regulation concering state aid, free of charge, temporary regulatory sandboxes for a project led by SME or SMEs, that has been approved as a strategic net-zero project.
2023/06/23
Committee: ITRE
Amendment 1440 #
Proposal for a regulation
Article 29 – paragraph 1
1. The Platform shall be composed of the Member States and of the Commission, the Commission, of the European Parliament, and of representatives of the industrials alliances. It shall be chaired by a representative of the Commission.
2023/06/23
Committee: ITRE
Amendment 1446 #
Proposal for a regulation
Article 29 – paragraph 2
2. Each Member State and the European Parliament shall appoint a high- level representative to the Platform. Where relevant as regards the function and expertise, a Member State and the European Parliament may have more than one representative in relation to different tasks related to the work of the Platform. Each member of the Platform shall have an alternate.
2023/06/23
Committee: ITRE
Amendment 1458 #
Proposal for a regulation
Article 29 – paragraph 7
7. The Platform shall invite representatives of the European Parliament to attend, as observers, its meetings, including of the standing or temporary sub-groups referred to in paragraph 6.deleted
2023/06/23
Committee: ITRE
Amendment 1462 #
Proposal for a regulation
Article 29 – paragraph 8
8. Where appropriate, the Platform or the Commission may invite experts and other third parties to Platform and sub- group meetings or to provide written contributions. Particular weight shall be given to representatives of SMEs, who shall be invited to take part in all meetings and discussions that concern them or their involvement, both on Platform and subgroup level.
2023/06/23
Committee: ITRE
Amendment 1499 #
Proposal for a regulation
Article 31 – paragraph 2 – point h a (new)
(ha) the participation of SMEs in net- zero strategic projects.
2023/06/23
Committee: ITRE
Amendment 1503 #
Proposal for a regulation
Article 31 – paragraph 2 a (new)
2a. the number of SMEs that are part of net-zero technology manufacturing projects;
2023/06/23
Committee: ITRE
Amendment 1550 #
Proposal for a regulation
Annex I – table 1
1. Solar photovoltaic and solar thermal technologies 2. Onshore wind and offshore renewable technologies 3. Battery/storageStorage technologies, including battery technologies 4. Heat pumps and geothermal energy technologies 5. Electrolysers and fuel cells 6. Sustainable biogas/biomethane technologies 7. Carbon Capture and, storage (CCS) technologies 8. Grid technologies
2023/06/23
Committee: ITRE
Amendment 1551 #
Proposal for a regulation
Annex I – table 1
1. Solar photovoltaic and solar thermal technologies 2. Onshore wind and offshore renewable technologies 3. Battery/sStorage technologies 4. Heat pumps and geothermal energy technologies 5. Electrolysers and fuel cells 6. Sustainable alternative fuel technologies, including biogas/biomethane technologies 7. Carbon Capture and, storage (CCS) technologies 8. Grid technologies
2023/06/23
Committee: ITRE
Amendment 1552 #
Proposal for a regulation
Annex I – table 1
1. Solar photovoltaic and solar thermal technologies 2. Onshore wind and offshore renewable technologies 3. Battery/sStorage technologies 4. Heat pumps and geothermal energy technologies 5. Electrolysers and fuel cells 6. Sustainable biogas/biomethane technologies 7. Carbon Capture and, storage (CCS) and Carbon Capture and Utilisation (CCU) technologies 8. Grid technologies
2023/06/23
Committee: ITRE