BETA

7 Amendments of Emma WIESNER related to 2022/0160(COD)

Amendment 60 #
Proposal for a directive
Recital 15
(15) The designation of renewables go- to areas should allow renewable energy plants, their grid connection as well as co- located energy storage facilities located in these areas to benefit from predictability and streamlined administrative procedures. In particular, projects located in renewable go-to areas should benefit from accelerated administrative procedures, including a tacit agreement in case of a lack of response by the competent authority on an administrative step by the established deadline, unless the specific project is subject to an environmental impact assessment. These projects should also benefit from clearly delimited deadlines and legal certainty as regards the expected outcome of the procedure. Following the application for projects in a renewables go- to area, Member States should carry out a fast screening of such applications with the aim to identify if any of such projects is highly likely to give rise to significant unforeseen adverse effects in view of the environmental sensitivity of the geographic area where they are located that were not identified during the environmental assessment of the plan or plans designating renewables go-to areas carried out in accordance with Directive 2001/42/EC. All projects located in renewables go-to areas should be deemed approved at the end of such screening process. Only if Member States have clear evidence to consider that a specific project is highly likely to give rise to such significant unforeseen adverse effects, Member States should, after motivating such decision, subject such project to an environmental assessment in accordance with Directive 2011/92/EC and, where relevant, Directive 92/43/EEC25 . Given the need to accelerate the deployment of renewable energy sources, such assessment should be carried out within six months. _________________ 25 Council Directive 92/43/EEC of 21 May 1992 on the convervation of natural habitats and of wild fauna and flora (OJ L 206, 22.7.1992).
2022/09/29
Committee: ITRE
Amendment 74 #
Proposal for a directive
Recital 21
(21) The installation of solar energy equipment, together with related co-located storage and grid connection, in existing or future structures created for purposes different than solar energy production with the exclusion of artificial water surfaces, such as rooftops, parking areas, roads and railways, do not typically raise concerns related to competing uses of space or environmental impact. These installations therefore may benefit from shorter permit- granting procedures.
2022/09/29
Committee: ITRE
Amendment 186 #
Proposal for a directive
Article 1 – paragraph 1 – point 5
Directive (EU) 2018/2001
Article 15c – paragraph 1 – subparagraph 1 – point b
(b) Establish appropriate rules for the designated renewable go-to areas, including on the mitigation measures to be adopted for the installation of renewable energy plants, co-located energy storage facilities, as well as assets necessary for their connection to the grid, in order to avoid or, if not possible, to significantly reduce the negative environmental impacts that may arise. Where appropriate, Member States shall ensure that appropriate mitigation measures are applied to prevent the situations described in Articles 6(2) and 12(1) of Directive 92/43/EEC, Article 5 of Directive 2009/147/EEC and Article 4(1)(a)(i) and (ii) of Directive 2000/60/EC. Such rules shall be targeted to the specificities of each identified renewable go-to area, the renewable energy technology or technologies to be deployed in each area and the identified environmental impacts. Compliance with such rules and the implementation of the appropriate mitigation measures by the individual projects shall result in the presumption that projects are not in breach of those provisions without prejudice to paragraphs 4 and 5 of Article 16a. Where novel mitigation measures to prevent as much as possible the killing or disturbance of species protected under Council Directive 92/43/EEC and Directive 2009/147/EEC, or any other environmental impact, have not been widely tested as regards their effectiveness, Member States may allow their use for one or several pilot projects for a limited time period, provided that the effectiveness of such measures is closely monitored and appropriate steps are taken immediately if they do not prove to be effective. .
2022/09/29
Committee: ITRE
Amendment 204 #
Proposal for a directive
Article 1 – paragraph 1 – point 6
Directive (EU) 2018/2001
Article 16 – paragraph 1
(1) The permit-granting process shall cover all relevant administrative permits to build, repower and operate plants for the production of energy from renewable sources, co-located energy storage facilities, as well as assets necessary for their connection to the grid and the relevant transmission and distribution network elements, including grid connection permits and environmental assessments where these are required. The permit-granting process shall comprise all procedures from the acknowledgment of the validity of the application in accordance with paragraph 2 to the notification of the final decision on the outcome of the procedure by the relevant authority or authorities.
2022/09/29
Committee: ITRE
Amendment 244 #
Proposal for a directive
Article 1 – paragraph 1 – point 7
Directive (EU) 2018/2001
Article 16a Paragraph 2
(2) The permit-granting process for the repowering of plants and for new installations with an electrical capacity of less than 150 kW, co-located energy storage facilities as well as their grid connection, located in renewables go-to areas shall not exceed six months. Where duly justified on the ground of extraordinary circumstances, such as on grounds of overriding safety reasons where the repowering project impacts substantially on the grid or the original capacity, size or performance of the installation, that one year period may be extended by up to three months. Member States shall clearly inform the project developer about the extraordinary circumstances that justify the extension.
2022/09/29
Committee: ITRE
Amendment 249 #
Proposal for a directive
Article 1 – paragraph 1 – point 7
Directive (EU) 2018/2001
Article 16a – paragraph 3 – subparagraph 1
Without prejudice to paragraphs 4 and 5, by derogation from Article 4(2) of Directive 2011/92/EU, and Annex II, points 3(a), (b), (d), (h), (i), and 6(c) alone or in conjunction with point 13(a) to that Directive as far as this concerns renewable energy projects, new applications for renewable energy plants, except for biomass combustion plants, including the repowering of plants, in already designated renewables go-to areas for the respective technology, co-located storage facilities in already designated renewables go-to areas as well as their connection to the grid, shall be exempted from the requirement to carry out a dedicated environmental impact assessment under Article 2(1) of Directive 2011/92/EU, provided that these projects comply with the rules and measures set out in accordance with Article 15c(1), point (b). The exemption from the application of Directive 2011/92/EU above shall not apply to projects which are likely to have significant effects on the environment in another Member State or where a Member State likely to be significantly affected so requests, as provided for in Article 7 of the said Directive.
2022/09/29
Committee: ITRE
Amendment 277 #
Proposal for a directive
Article 1 – paragraph 1 – point 8
Directive (EU) 2018/2001
Article 16b – paragraph 2 – subparagraph 1
Where an environmental assessment is required under Directive 2011/92/EU or Directive 92/43/EEC, it shall be carried out in a single procedure that combines all relevant assessments for a given project. When any such environmental impact assessment is required, the competent authority, taking into account the information provided by the developer, shall issue an opinion on the scope and level of detail of the information to be included by the developer in the environmental impact assessment report, of which the scope shall not be extended subsequently. Where the specific projects have adopted appropriate mitigation measures, any killing or disturbance of the species protected under Article 12(1) of Directive 92/43/EEC and Article 5 of Directive 2009/147/EC shall not be considered deliberate. Where novel mitigation measures to prevent as much as possible the killing or disturbance of species protected under Council Directive 92/43/EEC and Directive 2009/147/EEC, or any other environmental impact, have not been widely tested as regards their effectiveness, Member States may allow their use for one or several pilot projects for a limited time period, provided that the effectiveness of such measures is closely monitored and appropriate steps are taken immediately if they do not prove to be effective. The permit-granting process for the repowering of projects and for new installations with an electrical capacity of less than 150 kW, co-located storage facilities as well as their grid connection, located outside renewables go-to areas shall not exceed one year including environmental assessments where required by relevant legislation. Where duly justified on the ground of extraordinary circumstances, this one-year period may be extended by up to three months. Member States shall clearly inform the developers about the extraordinary circumstances that justified the extension.
2022/09/29
Committee: ITRE