Progress: Procedure completed
Role | Committee | Rapporteur | Shadows |
---|---|---|---|
Lead | LIBE | COELHO Carlos ( PPE) | |
Committee Opinion | BUDG | PICKART ALVARO Alexander Nuno ( ALDE) |
Lead committee dossier:
Legal Basis:
TFEU 074
Legal Basis:
TFEU 074Events
The Commission presents a Staff Working Document reporting on the global schedule and budget for the entry into operation of the second generation Schengen Information System (SIS II). It recalls that it presented to the Justice and Home Affairs (JHA) Council of 3-4 June 2010 a revised project schedule whereby SIS II could be expected to become operational by the first quarter of 2013. No information on the budgetary estimate was given at that time, as costs for the completion of the project were mainly dependent on contractual negotiations still to be launched during the summer. Both the global schedule and the budgetary estimate are to be confirmed at the forthcoming JHA Council of 7-8 October 2010. This report is also intended to provide information to the European Parliament, in its capacity of budgetary authority, a transparent and timely manner. It provides supporting information on the detailed global schedule and budgetary estimate, in particular the main assumptions and technical elements on which they were developed. It builds upon the intensive preparatory work carried out with Member States' experts and the subsequent negotiations with the main development contractor.
The SIS II project has had a difficult evolution. The challenge for all stakeholders has been to adapt and respond to the significant increase in the number of users (following EU enlargement), the intensity of use of the existing SIS by Member States authorities, as well as the need to reach a common understanding on the definitive operational requirements of the system. The original specifications anticipated the management of 15 million records, increasing over time to 22 million. However, due to the expansion in the number of Member States using the SIS and the intensive use of the system by the competent authorities, by January 2010 the existing system had arrived at over 31 million alerts. On this basis, experts agreed that the estimated size of SIS II at go-live was likely to be 52 million alerts.
Accordingly, it was agreed that the system capacity at entry-into-operation should be increased to 70 million alerts and that SIS II should be tested with a view to ensuring a scalability up to 100 million alerts without the need for technical change. The scale of the system's volumetric growth would thus exceed the capacity and the scalability obligations as laid down in the initial contract. This deviation from the original specifications has a significant impact on the hardware, requiring its adaptation and installation on several additional technical environments (dedicated hardware configurations for different development and testing needs).
Thanks to a collaborative approach with Member States and transparent information exchange with the European Parliament, and on the basis of commonly agreed definitive requirements, the Commission is now in a position to confirm the global schedule and present the budgetary plan for the entire project. Accordingly, SIS II will enter into operation in early 2013 . The further development of the system and the increase of its capacity require an additional allocation of EUR 12.98 million , compared to the estimate presented to the Council and Parliament in June 2009 and April 2010. This amount is within the overall budgetary envelope for SIS II agreed by Council and the European Parliament for the period 2007-2013.
PURPOSE: to amend Decision 2008/839/JHA on migration from the Schengen Information System (SIS 1+) to the second generation Schengen Information System (SIS II) in order to provide a new expiry date.
LEGISLATIVE ACT: Council Regulation (EU) No 542/2010 amending Decision 2008/839/JHA on migration from the Schengen Information System (SIS 1+) to the second generation Schengen Information System (SIS II).
BACKGROUND: the Schengen Information System (SIS) was established in 1985 between the governments of the States of the Benelux Economic Union, Germany and France on the gradual abolition of checks at their common borders (the Schengen Convention), and its development, SIS 1+, constitute an essential tool for the application of the provisions of the Schengen acquis as integrated into the framework of the European Union.
The development of the second generation of SIS (SIS II) has been entrusted to the Commission pursuant to Council Regulation (EC) No 2424/2001 and Council Decision 2001/886/JHA on the development of the second generation Schengen Information System (SIS II). SIS II will replace SIS 1+. SIS II development takes into account the latest evolutions in the field of information technology and allows the introduction of added functionalities.
Provisions on the establishment, operation and use of SIS II are laid down in Regulation (EC) No. 1987/2006 of the European Parliament and of the Council and Council Decision 2007/533/JHA . These instruments foresee that they will apply to the Member States participating in SIS 1+ only as of dates to be fixed by the Council, acting by the unanimity of its Members representing the governments of the Member States participating in SIS 1+. They will then replace the provisions of the Schengen acquis governing SIS 1+, in particular the relevant provisions in the Schengen Convention.
Before this can happen, the users of the SIS 1+ will have to migrate to the SIS II environment . A legal framework for the migration from SIS 1+ to the SIS II environment was therefore designed. In order to reduce the risks of service disruption during migration an interim technical architecture for the operations of SIS 1+ will allow SIS 1+ and certain technical parts of the architecture of SIS II to operate in parallel for a transitional period.
The time-frame of the current migration instruments ( Council Decision 2008/839/JHA and Council Regulation (EC) No 1104/2008 ), and in particular their date of expiry which is currently set to be 30 June 2010 at the latest, appears no longer realistic . This Regulation therefore aims to amend the expiry date of Decision 839/2008/JHA and to provide an alternative technical solution if migration fails.
CONTENT: Decision 2008/839/JHA is amended as follows
Extending the expiry date of Decision 2008/839/JHA : the Regulation extends until 31 March 2013 the preconditions for migration from SIS 1 to SIS II.
Global Programme Management Board : the Regulation establishes a group of technical experts, called the Global Programme Management Board. The Board shall be an advisory body for assistance to the central SIS II project and shall facilitate consistency between central and national SIS II projects. The Board shall have no decision-making power nor any mandate to represent the Commission or Member States. It shall be composed of a maximum of 10 members, meeting on a regular basis. A maximum of 8 experts and an equal number of alternates shall be designated by the Member States acting within the Council. A maximum of two experts and two alternates shall be designated by the Director-General of the responsible Directorate-General of the Commission from among the Commission officials. The meetings of the Board may be attended by other Member States’ experts and Commission officials directly involved in the development of the SIS II projects, at the expense of their respective administration or institution. The Board shall regularly submit written reports about the progress of the project. The administrative costs and travel expenses arising from the activities of the Board shall be borne by the general budget of the Union.
Towards an alternative technical scenario in case migration fails : the Regulation states that a study has been conducted concerning the elaboration of an alternative technical scenario for developing SIS II based on SIS 1+ evolution (SIS 1+ RE) as the contingency plan, in case the tests demonstrate non-compliance with the milestone requirements. Based on these parameters, the Council may decide to invite the Commission to switch to the alternative technical scenario. SIS 1+ RE could be a possible technical solution to develop Central SIS II and to achieve the objectives of the SIS II laid down in Regulation (EC) No 1987/2006 and Decision 2007/533/JHA.
As regards the financing of the development of the Central SIS II based on an alternative technical solution , it should be covered by the general budget of the Union.
In case of a switchover to an alternative technical scenario, the date to be noted for the expiration of Decision 839/2008/JHA shall be 31 December 2013 .
Territorial application : Denmark is not taking part in the adoption of this Regulation and is not bound by it or subject to its application. It may decide within a period of six months after the Council has decided on this Regulation whether it will implement it in its national law. The United Kingdom and Ireland will participate. Lastly, Iceland, Norway, Switzerland and Liechtenstein will be associated in the implementation of this Regulation.
ENTRY INTO FORCE: 25 June 2010.
The European Parliament adopted by 547 votes to 36 with 42 abstentions a resolution on the proposal for a Council regulation amending Decision 2008/839/JHA on migration from the Schengen Information System (SIS 1+) to the second generation Schengen Information System (SIS II) It amended the Commission proposal as follows:
Towards a technical solution in the case of a failure of the SIS II : it is necessary to adapt the legal framework to allow for migration to a possible alternative technical solution if tests show that SIS II cannot be implemented successfully. Members propose that in the event of a failure of the current SIS II project, after testing, an alternative technical solution should be devised and its full financial implications should be disclosed to all parties concerned. This solution should be based on the best available technology and should be cost-effective and implemented in accordance with a precise and reasonable timetable . The Commission should present a thorough budgetary assessment of the costs associated with such an alternative technical solution in a timely fashion. It should be explicitly stated that the legal framework established by Decision 2007/533/JHA applies to every solution, regardless of its technical nature.
Similarly, if the current SIS II project is discontinued and an alternative technical solution is implemented, references to SIS II in this Decision shall be read as references to that alternative technical solution.
Maintaining the sunset clause : the current legislation sets the date for the completion of the migration at 30 September 2009, with the possibility for extension, through comitology, until 30 June 2010 at the latest. The Commission did use this and extended the date until 30 June 2010. However, Members consider that the sunset clause should be kept . The new date should be in line with the current forecasts that SIS II will become operational by the end of 2011. The Commission should be granted some flexibility again to extend the date through comitology, in order to cover the possible need to switch from SIS II to an alternative scenario in case the tests fail. Accordingly, the text now provides that Member States participating in SIS 1+ shall migrate from N.SIS to N.SIS II using the interim migration architecture, with the support of France and of the Commission by 31 December 2011 at the latest. If an alternative technical solution is implemented, that date may be changed in accordance with the comitology procedure specified in the text. .It should also be noted that this Regulation shall expire no later than on 31 December 2013.
Full association of the European Parliament as co-legislator : as the European Parliament is responsible as a co-legislator for the establishment, operation and use of SIS II as laid down in Regulation (EC) No 1987/2006, and as the migration is financed from the Union budget, for which the European Parliament is also co-responsible, the European Parliament should be integrated in the decision making process concerning migration. A favourable opinion from the European Parliament, on the basis of information provided by the Commission on the test results, should be required before the switchover to a new Schengen Information System.
Global Programme Management Board (GPMB) : the GPMB shall be composed of a maximum of 10 members who shall be qualified contribute actively to the development of the SIS II and who shall meet on a regular basis. Members stipulate that interested Members or relevant staff of the European Parliament, experts from Member States and Commission officials directly involved in the development of the SIS II projects may attend GPMB meetings at the expense of their respective administration or institution. The GPMB may invite other experts to participate in GPMB meetings as defined in the terms of reference at the expense of their respective administration, institution or company. The necessary appropriations to cover the cost arising from the meetings of the GPMB shall come from the appropriations currently provided for in the Financial Programming 2010-2013 for the second generation Schengen Information System (SIS II).
The mandate of the GPMB: Parliament added that the GPMB shall provide a forum for assistance to the development of Central SIS II. It should facilitate consistency and provide for coordination of the central and national SIS II projects. The terms of reference of the GPMB shall include a requirement to publish regular reports and to make those reports available to the European Parliament in order to ensure full parliamentary scrutiny and oversight.
Personal data : Parliament added that the Commission shall develop and implement a package with additional measures in order to prevent the leakage of personal data information from the database and to ensure the protection of personal data for the entire duration of testing and migration from SIS I to the second generation Schengen Information System (SIS II).
It should be noted that the legislative resolution specifies that the Parliament, as co-legislator for the establishment of the second generation Schengen Information System (SIS II) and budgetary authority, reserves its right to hold in reserve the funds to be allocated for the development of the SIS II in the 2011 annual budget, in order to ensure full parliamentary scrutiny and oversight of the process.
The Committee on Civil Liberties, Justice and Home Affairs adopted the report by Carlos COELHO (EPP, PT) amending the proposal for a Council regulation amending Decision 2008/839/JHA on migration from the Schengen Information System (SIS 1+) to the second generation Schengen Information System (SIS II).
The main amendments were as follows:
Towards a technical solution in the case of a failure of the SIS II : it is necessary to adapt the legal framework to allow for migration to a possible alternative technical solution if tests show that SIS II cannot be implemented successfully. Members propose that in the event of a failure of the current SIS II project, after testing, an alternative technical solution should be devised and its full financial implications should be disclosed to all parties concerned. This solution should be based on the best available technology and should be cost-effective and implemented in accordance with a precise and reasonable timetable . The Commission should present a thorough budgetary assessment of the costs associated with such an alternative technical solution in a timely fashion. It should be explicitly stated that the legal framework established by Decision 2007/533/JHA applies to every solution, regardless of its technical nature.
Similarly, if the current SIS II project is discontinued and an alternative technical solution is implemented, references to SIS II in this Decision shall be read as references to that alternative technical solution.
Maintaining the sunset clause : the current legislation sets the date for the completion of the migration at 30 September 2009, with the possibility for extension, through comitology, until 30 June 2010 at the latest. The Commission did use this and extended the date until 30 June 2010. On the contrary, Members consider that the sunset clause should be kept . The new date should be in line with the current forecasts that SIS II will become operational by the end of 2011. The Commission should be granted some flexibility again to extend the date through comitology, in order to cover the possible need to switch from SIS II to an alternative scenario in case the tests fail. It should also be noted that this Regulation shall expire no later than on 31 December 2013 .
Full association of the European Parliament as co-legislator : as the European Parliament is responsible as a co-legislator for the establishment, operation and use of SIS II as laid down in Regulation (EC) No 1987/2006, and as the migration is financed from the Union budget, for which the European Parliament is also co-responsible, the European Parliament should be integrated in the decision making process concerning migration. A favourable opinion from the European Parliament, on the basis of information provided by the Commission on the test results, should be required before the switchover to a new Schengen Information System.
Moreover, Members state that the European Parliament, as co-legislator for the establishment of the second generation Schengen Information System (SIS II) (Regulation (EC) No 1987/2006) and budgetary authority, reserves its right to hold in reserve the funds to be allocated for the development of the SIS II in the 2011 annual budget , in order to ensure full parliamentary scrutiny and oversight of the process.
Global Programme Management Board (GPMB) : the GPMB shall be composed of a maximum of 10 members who shall be qualified contribute actively to the development of the SIS II and who shall meet on a regular basis. Members stipulate that interested Members or relevant staff of the European Parliament, experts from Member States and Commission officials directly involved in the development of the SIS II projects may attend GPMB meetings at the expense of their respective administration or institution. The GPMB may invite other experts to participate in GPMB meetings as defined in the terms of reference at the expense of their respective administration, institution or company. The necessary appropriations to cover the cost arising from the meetings of the GPMB shall come from the appropriations currently provided for in the Financial Programming 2010-2013 for the second generation Schengen Information System (SIS II).
The mandate of the GPMB should be more clearly defined, in order to enable it to contribute actively to the management of the development of the second-generation SIS and the migration process. The GPMB shall provide a forum for assistance to the development of Central SIS II. It should facilitate consistency and provide for coordination of the central and national SIS II projects. The terms of reference of the GPMB shall include a requirement to publish regular reports and to make those reports available to the European Parliament in order to ensure full parliamentary scrutiny and oversight.
PURPOSE: to amend Decision 2008/839/JHA on migration from the Schengen Information System (SIS 1+) to the second generation Schengen Information System (SIS II) in order to postpone its expiry date.
PROPOSED ACT: Council Regulation.
BACKGROUND: the Schengen Information System (SIS) was established in 1985 between the governments of the States of the Benelux Economic Union, Germany and France on the gradual abolition of checks at their common borders, and its development, SIS 1+, constitute an essential tool for the application of the provisions of the Schengen acquis as integrated into the framework of the European Union.
The development of the second generation of SIS (SIS II) has been entrusted to the Commission pursuant to Council Regulation (EC) No 2424/2001 and Council Decision 2001/886/JHA on the development of the second generation Schengen Information System (SIS II). SIS II will replace SIS 1+ which has become obsolete and no longer responds to the needs of the enlarged European Union.
Provisions on the establishment, operation and use of SIS II are laid down in Regulation (EC) No. 1987/2006 of the European Parliament and of the Council on the establishment, operation and use of the second generation Schengen Information System (SIS II) and Council Decision 2007/533/JHA on the establishment, operation and use of the second generation Schengen Information System (SIS II). These instruments foresee that they will apply to the Member States participating in SIS 1+ only as of dates to be fixed by the Council, acting by the unanimity of its Members representing the governments of the Member States participating in SIS 1+. They will then replace the provisions of the Schengen acquis governing SIS 1+, in particular the relevant provisions in the Schengen Convention.
Before this can happen, the users of the SIS 1+ will have to migrate to the SIS II environment . A legal framework for the migration from SIS 1+ to the SIS II environment was therefore designed. In order to reduce the risks of service disruption during migration an interim technical architecture for the operations of SIS 1+ will allow SIS 1+ and certain technical parts of the architecture of SIS II to operate in parallel for a transitional period.
However, the time-frame of the current migration instruments ( Council Decision 2008/839/JHA and Council Regulation No 1104/2008 ), and in particular their date of expiry which is currently set to be 30 June 2010 at the latest, appears no longer realistic . This proposal therefore aims at preventing expiry of Council Decision 2008/839/JHA before migration will take place. For legal reasons, this proposal only amends the decision.
CONTENT: the objective of the present proposal is to prevent expiry of Council Decision 2008/839/JHA before migration , as well as to:
· to ensure legal flexibility for an alternative technical scenario to attain SIS II functionalities based on SIS 1+, in case a switchover to this scenario should take place;
· to render management of SIS II development and migration, in particular regarding coordination of Commission and Member State projects, as efficient as possible. In order to achieve the latter objective, the GPMB is set up as an expert group at global programme level . The GPMB's role would be to act as a focal point between the actors and stakeholders involved in global SIS II development. In particular, it would allow the Commission and the Member States to coordinate the global programme in keeping with their respective responsibilities and activities regarding the central and national SIS II projects. The GPMB shall be composed of maximum of 10 experts. The administrative costs and travel expenses arising from the activities of the GPMB shall be borne by the general budget of the European Union. Transparency of the SIS II development process for the European Parliament is maintained through the existing reporting obligation.
Legal elements of the proposal : it should be noted that this proposal is being submitted as a Regulation under the appropriate legal basis of the Treaty on the Functioning of the European Union which has recently entered into force. The proposal is complemented by a proposed parallel Regulation on the same issue (see NLE/2009/0136 ).
Territorial application : due to reasons of a legal nature laid down in the Treaty, the United Kingdom and Ireland will only be associated for part of the implementation and the application of the present text (application of the “variable geometry” system). It also applies to Denmark, however it may decide, within a period of six months after the adoption of this Regulation, whether it will implement it in its national law. Lastly, Norway, Iceland, Switzerland and Liechtenstein will be associated with the implementation of this text in accordance with the bilateral agreements concluded with the EU on the Schengen acquis.
IMPACT ASSESSMENT: non applicable.
BUDGETARY IMPLICATIONS: the costs of setting up, operating and maintaining Central SIS II and the communication infrastructure are to be borne by the general budget of the European Union. The costs of setting up, operating and maintaining each N.SIS II shall be borne by the Member State concerned.
Under Article 15 of Regulation (EC) No 1104/2008 and Council Decision 2008/839/JHA as they have been phrased heretofore, additional costs for migration, testing, maintenance and development measures at the central level (Central SIS II and Communication Infrastructure) had been allocated to the general budget of the European Union as well. Testing, migration, maintenance and development costs for the national systems, including N.SIS II, have continued to be borne by each Member State concerned.
The present proposal does not modify this basic structure. It will, however, extend the existing legal basis to cover the post-30 June 2010 period until migration .
In addition, the cost arising from the meetings of the GPMB which is being set up by this proposal, including expenses for members and experts attending, would be borne by the general budget of the European Union. The necessary appropriations to cover the cost arising from the meetings of the GPMB will come from the appropriations currently foreseen in the Financial Programming 2010-2013 for the Schengen Information System (SIS II).
The Commission has prepared a financial statement annexed to this proposal which provides a budget of EUR 12.850 million in operational expenditure until 2012 (only costs caused by prolongation of the development and migration phase beyond 30 June 2010, will be taken into account. This excludes costs to be committed until 30 June 2010).
PURPOSE: to amend Decision 2008/839/JHA on migration from the Schengen Information System (SIS 1+) to the second generation Schengen Information System (SIS II) in order to postpone its expiry date.
PROPOSED ACT: Council Regulation.
BACKGROUND: the Schengen Information System (SIS) was established in 1985 between the governments of the States of the Benelux Economic Union, Germany and France on the gradual abolition of checks at their common borders, and its development, SIS 1+, constitute an essential tool for the application of the provisions of the Schengen acquis as integrated into the framework of the European Union.
The development of the second generation of SIS (SIS II) has been entrusted to the Commission pursuant to Council Regulation (EC) No 2424/2001 and Council Decision 2001/886/JHA on the development of the second generation Schengen Information System (SIS II). SIS II will replace SIS 1+ which has become obsolete and no longer responds to the needs of the enlarged European Union.
Provisions on the establishment, operation and use of SIS II are laid down in Regulation (EC) No. 1987/2006 of the European Parliament and of the Council on the establishment, operation and use of the second generation Schengen Information System (SIS II) and Council Decision 2007/533/JHA on the establishment, operation and use of the second generation Schengen Information System (SIS II). These instruments foresee that they will apply to the Member States participating in SIS 1+ only as of dates to be fixed by the Council, acting by the unanimity of its Members representing the governments of the Member States participating in SIS 1+. They will then replace the provisions of the Schengen acquis governing SIS 1+, in particular the relevant provisions in the Schengen Convention.
Before this can happen, the users of the SIS 1+ will have to migrate to the SIS II environment . A legal framework for the migration from SIS 1+ to the SIS II environment was therefore designed. In order to reduce the risks of service disruption during migration an interim technical architecture for the operations of SIS 1+ will allow SIS 1+ and certain technical parts of the architecture of SIS II to operate in parallel for a transitional period.
However, the time-frame of the current migration instruments ( Council Decision 2008/839/JHA and Council Regulation No 1104/2008 ), and in particular their date of expiry which is currently set to be 30 June 2010 at the latest, appears no longer realistic . This proposal therefore aims at preventing expiry of Council Decision 2008/839/JHA before migration will take place. For legal reasons, this proposal only amends the decision.
CONTENT: the objective of the present proposal is to prevent expiry of Council Decision 2008/839/JHA before migration , as well as to:
· to ensure legal flexibility for an alternative technical scenario to attain SIS II functionalities based on SIS 1+, in case a switchover to this scenario should take place;
· to render management of SIS II development and migration, in particular regarding coordination of Commission and Member State projects, as efficient as possible. In order to achieve the latter objective, the GPMB is set up as an expert group at global programme level . The GPMB's role would be to act as a focal point between the actors and stakeholders involved in global SIS II development. In particular, it would allow the Commission and the Member States to coordinate the global programme in keeping with their respective responsibilities and activities regarding the central and national SIS II projects. The GPMB shall be composed of maximum of 10 experts. The administrative costs and travel expenses arising from the activities of the GPMB shall be borne by the general budget of the European Union. Transparency of the SIS II development process for the European Parliament is maintained through the existing reporting obligation.
Legal elements of the proposal : it should be noted that this proposal is being submitted as a Regulation under the appropriate legal basis of the Treaty on the Functioning of the European Union which has recently entered into force. The proposal is complemented by a proposed parallel Regulation on the same issue (see NLE/2009/0136 ).
Territorial application : due to reasons of a legal nature laid down in the Treaty, the United Kingdom and Ireland will only be associated for part of the implementation and the application of the present text (application of the “variable geometry” system). It also applies to Denmark, however it may decide, within a period of six months after the adoption of this Regulation, whether it will implement it in its national law. Lastly, Norway, Iceland, Switzerland and Liechtenstein will be associated with the implementation of this text in accordance with the bilateral agreements concluded with the EU on the Schengen acquis.
IMPACT ASSESSMENT: non applicable.
BUDGETARY IMPLICATIONS: the costs of setting up, operating and maintaining Central SIS II and the communication infrastructure are to be borne by the general budget of the European Union. The costs of setting up, operating and maintaining each N.SIS II shall be borne by the Member State concerned.
Under Article 15 of Regulation (EC) No 1104/2008 and Council Decision 2008/839/JHA as they have been phrased heretofore, additional costs for migration, testing, maintenance and development measures at the central level (Central SIS II and Communication Infrastructure) had been allocated to the general budget of the European Union as well. Testing, migration, maintenance and development costs for the national systems, including N.SIS II, have continued to be borne by each Member State concerned.
The present proposal does not modify this basic structure. It will, however, extend the existing legal basis to cover the post-30 June 2010 period until migration .
In addition, the cost arising from the meetings of the GPMB which is being set up by this proposal, including expenses for members and experts attending, would be borne by the general budget of the European Union. The necessary appropriations to cover the cost arising from the meetings of the GPMB will come from the appropriations currently foreseen in the Financial Programming 2010-2013 for the Schengen Information System (SIS II).
The Commission has prepared a financial statement annexed to this proposal which provides a budget of EUR 12.850 million in operational expenditure until 2012 (only costs caused by prolongation of the development and migration phase beyond 30 June 2010, will be taken into account. This excludes costs to be committed until 30 June 2010).
Documents
- Contribution: COM(2010)0015
- Follow-up document: SEC(2010)1138
- Follow-up document: EUR-Lex
- Commission response to text adopted in plenary: SP(2010)3805
- Final act published in Official Journal: Regulation 2010/542
- Final act published in Official Journal: OJ L 155 22.06.2010, p. 0023
- Results of vote in Parliament: Results of vote in Parliament
- Debate in Parliament: Debate in Parliament
- Decision by Parliament: T7-0162/2010
- Committee report tabled for plenary, 1st reading/single reading: A7-0127/2010
- Committee report tabled for plenary, 1st reading/single reading: A7-0127/2010
- Amendments tabled in committee: PE439.896
- Committee opinion: PE439.248
- Committee draft report: PE439.091
- Legislative proposal: COM(2010)0015
- Legislative proposal: EUR-Lex
- Legislative proposal published: COM(2010)0015
- Legislative proposal published: EUR-Lex
- Legislative proposal: COM(2010)0015 EUR-Lex
- Committee draft report: PE439.091
- Committee opinion: PE439.248
- Amendments tabled in committee: PE439.896
- Committee report tabled for plenary, 1st reading/single reading: A7-0127/2010
- Commission response to text adopted in plenary: SP(2010)3805
- Follow-up document: SEC(2010)1138 EUR-Lex
- Contribution: COM(2010)0015
Amendments | Dossier |
8 |
2010/0006(NLE)
2010/03/18
LIBE
8 amendments...
Amendment 12 #
Draft legislative resolution Paragraph 1 a (new) 1a. Notwithstanding the fact that Council is treating SIS 1+ RE as a contingency plan in the event of a failure of SIS II, the European Parliament, as co-legislator for the establishment of the second generation Schengen Information System (SIS II) (Regulation (EC) No 1987/20061) and budgetary authority, reserves its right to hold in reserve the funds to be allocated for the development of the SIS II in the 2011 annual budget, in order to ensure full parliamentary scrutiny and oversight of the process;
Amendment 13 #
Proposal for a regulation – amending act Recital 3 (3) The preconditions for migration will not be met by 30 June 2010. In order for SIS II to become operational as required by Regulation (EC) 1987/2006 and Decision 2007/533/JHA, Regulation (EC) No 1104/2008 and Decision 2008/839/JHA should therefore continue to apply until migration has been completed.
Amendment 14 #
Proposal for a regulation – amending act Recital 6 (6)
Amendment 15 #
Proposal for a regulation – amending act Article 1 – point 1 a (new) Council Decision 2008/839/JHA Article 5 – paragraph 1 a (new) (1a) In Article 5, the following paragraph is inserted: "1a. The Commission shall develop and implement a package with additional measures in order to prevent the leakage of personal data information from the database and to assure the protection of personal data for the entire duration of testing and migration from SIS I to the second generation Schengen Information System (SIS II)."
Amendment 16 #
Proposal for a regulation – amending act Article 1 – point 3 a (new) Council Decision 2008/839/JHA Article 14 – paragraph 3 (3a) In Article 14, paragraph 3 is replaced by the following: "(3) The records may only be used for the purposes referred to in paragraph 1 and shall be deleted automatically three years after their creation."
Amendment 17 #
Proposal for a regulation – amending act Article 1 – point 4 Council Decision 2008/839/JHA Article 17 a – paragraph 2 2. The GPMB shall be composed of a maximum of 10
Amendment 18 #
Proposal for a regulation – amending act Article 1 – point 4 Council Decision 2008/839/JHA Article 17 a – paragraph 5 5. The GPMB shall draw up its own terms of reference. They shall take effect after a
Amendment 19 #
Proposal for a regulation – amending act Article 1 – point 4 Council Decision 2008/839/JHA Article 17 a – paragraph 6 6. Without prejudice to Article 15(2), the administrative costs and travel expenses arising from the activities of the GPMB shall be borne by the general budget of the European Union, to the extent that they are not reimbursed from other sources. As regards travel expenses of the experts in the GPMB designated by the Member States acting within the Council and experts invited pursuant to paragraph 3 of this Article which arise in connection with the work of the GPMB, the Commission's 'Rules on the reimbursement of expenses incurred by people from outside the Commission invited to attend meetings in an expert capacity' shall apply. The necessary appropriations to cover the cost arising from the meetings of the GPMB shall come from the appropriations currently foreseen in the Financial Programming 2010-2013 for the second generation Schengen Information System (SIS II).
source: PE-439.896
|
History
(these mark the time of scraping, not the official date of the change)
docs/0 |
|
docs/4 |
|
docs/5 |
|
docs/5 |
|
docs/5/docs/0/url |
/oeil/spdoc.do?i=18315&j=0&l=en
|
docs/6 |
|
docs/6 |
|
docs/6/docs/0/url |
Old
http://www.europarl.europa.eu/registre/docs_autres_institutions/commission_europeenne/sec/2010/1138/COM_SEC(2010)1138_EN.pdfNew
http://www.europarl.europa.eu/RegData/docs_autres_institutions/commission_europeenne/sec/2010/1138/COM_SEC(2010)1138_EN.pdf |
docs/7 |
|
events/0/docs/0/url |
Old
http://www.europarl.europa.eu/RegData/docs_autres_institutions/commission_europeenne/com/2010/0015/COM_COM(2010)0015_EN.pdfNew
http://www.europarl.europa.eu/registre/docs_autres_institutions/commission_europeenne/com/2010/0015/COM_COM(2010)0015_EN.pdf |
links/National parliaments/url |
Old
http://www.ipex.eu/IPEXL-WEB/dossier/dossier.do?code=NLE&year=2010&number=0006&appLng=ENNew
https://ipexl.europarl.europa.eu/IPEXL-WEB/dossier/code=NLE&year=2010&number=0006&appLng=EN |
docs/0/docs/0/url |
Old
http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE439.091New
https://www.europarl.europa.eu/doceo/document/LIBE-PR-439091_EN.html |
docs/1/docs/0/url |
Old
http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE439.248&secondRef=03New
https://www.europarl.europa.eu/doceo/document/BUDG-AD-439248_EN.html |
docs/2/docs/0/url |
Old
http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE439.896New
https://www.europarl.europa.eu/doceo/document/LIBE-AM-439896_EN.html |
docs/3/docs/0/url |
Old
http://www.europarl.europa.eu/doceo/document/A-7-2010-0127_EN.htmlNew
https://www.europarl.europa.eu/doceo/document/A-7-2010-0127_EN.html |
docs/4/docs/0/url |
/oeil/spdoc.do?i=18315&j=0&l=en
|
events/1/type |
Old
Committee referral announced in Parliament, 1st reading/single readingNew
Committee referral announced in Parliament |
events/2/type |
Old
Vote in committee, 1st reading/single readingNew
Vote in committee |
events/3/docs/0/url |
Old
http://www.europarl.europa.eu/doceo/document/A-7-2010-0127_EN.htmlNew
https://www.europarl.europa.eu/doceo/document/A-7-2010-0127_EN.html |
events/5/docs/0/url |
Old
http://www.europarl.europa.eu/sides/getDoc.do?secondRef=TOC&language=EN&reference=20100518&type=CRENew
https://www.europarl.europa.eu/doceo/document/CRE-7-2010-05-18-TOC_EN.html |
events/6 |
|
events/6 |
|
procedure/Modified legal basis |
Rules of Procedure EP 150
|
procedure/Other legal basis |
Rules of Procedure EP 159
|
committees/0 |
|
committees/0 |
|
committees/1 |
|
committees/1 |
|
docs/3/docs/0/url |
Old
http://www.europarl.europa.eu/sides/getDoc.do?type=REPORT&mode=XML&reference=A7-2010-127&language=ENNew
http://www.europarl.europa.eu/doceo/document/A-7-2010-0127_EN.html |
docs/4/body |
EC
|
events/3/docs/0/url |
Old
http://www.europarl.europa.eu/sides/getDoc.do?type=REPORT&mode=XML&reference=A7-2010-127&language=ENNew
http://www.europarl.europa.eu/doceo/document/A-7-2010-0127_EN.html |
events/6/docs/0/url |
Old
http://www.europarl.europa.eu/sides/getDoc.do?type=TA&language=EN&reference=P7-TA-2010-162New
http://www.europarl.europa.eu/doceo/document/TA-7-2010-0162_EN.html |
activities |
|
commission |
|
committees/0 |
|
committees/0 |
|
committees/1 |
|
committees/1 |
|
council |
|
docs |
|
events |
|
other |
|
procedure/Modified legal basis |
Old
Rules of Procedure of the European Parliament EP 150New
Rules of Procedure EP 150 |
procedure/dossier_of_the_committee |
Old
LIBE/7/02186New
|
procedure/final/url |
Old
http://eur-lex.europa.eu/smartapi/cgi/sga_doc?smartapi!celexplus!prod!CELEXnumdoc&lg=EN&numdoc=32010R0542New
https://eur-lex.europa.eu/smartapi/cgi/sga_doc?smartapi!celexplus!prod!CELEXnumdoc&lg=EN&numdoc=32010R0542 |
procedure/instrument |
Old
RegulationNew
|
procedure/subject |
Old
New
|
procedure/summary |
|
activities/0/docs/0/url |
Old
http://www.europarl.europa.eu/registre/docs_autres_institutions/commission_europeenne/com/2010/0015/COM_COM(2010)0015_EN.pdfNew
http://www.europarl.europa.eu/RegData/docs_autres_institutions/commission_europeenne/com/2010/0015/COM_COM(2010)0015_EN.pdf |
links/European Commission/title |
Old
PreLexNew
EUR-Lex |
activities |
|
committees |
|
links |
|
other |
|
procedure |
|