BETA


2012/2017(DEC) Special report 16/2011 (2011 discharge): EU financial assistance for the decommissioning of nuclear plants in Bulgaria, Lithuania and Slovakia: achievements and future challenges

Progress: Procedure lapsed or withdrawn

RoleCommitteeRapporteurShadows
CONT MARINESCU Marian-Jean (icon: ) BALČYTIS Zigmantas (icon: ), STAES Bart (icon: ), CZARNECKI Ryszard (icon: ), SØNDERGAARD Søren Bo (icon: ), ANDREASEN Marta (icon: ), EHRENHAUSER Martin (icon: )
ITRE
Lead committee dossier:
Legal Basis:
RoP 99

Events

2012/02/16
   EP - Committee referral announced in Parliament
2012/02/08
   CofA - Non-legislative basic document
Details

PURPOSE: to present the ECA special report 16/2011 on EU financial assistance for the decommissioning of nuclear plants in Bulgaria, Lithuania and Slovakia.

CONTENT: in order to increase nuclear safety, Bulgaria, Lithuania and Slovakia committed themselves within their EU accession negotiations to the early closure and subsequent decommissioning of eight non-upgradeable nuclear reactors.

Recognizing the exceptional social, economic and financial burden of their commitments, the EU provided financial assistance to the three country-programmes (EUR 2 850 million overall for the 1999-2013 period).

This special report deals with the implementation of the decommissioning programmes from 1999 up to the end of 2010. The audit examined whether EU funded actions have been designed in accord with identified needs and carried out as planned, and whether the governance arrangements have been adequate.

Court’s conclusions : the Court found that while Bulgaria, Lithuania and Slovakia have closed the reactors in line with their commitment, and important milestones have been achieved in decommissioning, the main process is still ahead and its finalisation faces a significant funding shortfall (around EUR 2.5 billion).

The Court notes the following:

the identification of decommissioning activities is still in progress; major infrastructure projects face delays and cost-overruns; cost estimates are not complete in the absence of key information on radioactive waste and/or the facilities and technologies required for their treatment; a broad variety of activities to mitigate the consequences of the nuclear reactors’ early closure has been financed but the degree of mitigation achieved is not known; there is no comprehensive needs-assessment, prioritization and setting of specific objectives. Responsibilities are diffused. The Commission’s supervision focuses on the budgetary execution and project implementation rather than on the achievement of the programme objectives as a whole.

Court’s recommendations : the Court recommends that the Commission should establish a detailed needs-assessment showing the progress of the programmes, the activities still to be performed and an overall financing plan identifying the funding sources. Before further spending takes place, t he Commission should analyse the resources available and the expected benefits . This should lead in turn to objectives being aligned with the resources and to performance indicators which can subsequently be monitored and reported on as necessary.

Further financial assistance after 2013 should be based on an evaluation of its EU added value, identifying the specific activities to be financed taking account of other funding facilities, such as Structural Funds .

Documents
2012/02/07
   EC - Non-legislative basic document published
Details

PURPOSE: to present the ECA special report 16/2011 on EU financial assistance for the decommissioning of nuclear plants in Bulgaria, Lithuania and Slovakia.

CONTENT: in order to increase nuclear safety, Bulgaria, Lithuania and Slovakia committed themselves within their EU accession negotiations to the early closure and subsequent decommissioning of eight non-upgradeable nuclear reactors.

Recognizing the exceptional social, economic and financial burden of their commitments, the EU provided financial assistance to the three country-programmes (EUR 2 850 million overall for the 1999-2013 period).

This special report deals with the implementation of the decommissioning programmes from 1999 up to the end of 2010. The audit examined whether EU funded actions have been designed in accord with identified needs and carried out as planned, and whether the governance arrangements have been adequate.

Court’s conclusions : the Court found that while Bulgaria, Lithuania and Slovakia have closed the reactors in line with their commitment, and important milestones have been achieved in decommissioning, the main process is still ahead and its finalisation faces a significant funding shortfall (around EUR 2.5 billion).

The Court notes the following:

the identification of decommissioning activities is still in progress; major infrastructure projects face delays and cost-overruns; cost estimates are not complete in the absence of key information on radioactive waste and/or the facilities and technologies required for their treatment; a broad variety of activities to mitigate the consequences of the nuclear reactors’ early closure has been financed but the degree of mitigation achieved is not known; there is no comprehensive needs-assessment, prioritization and setting of specific objectives. Responsibilities are diffused. The Commission’s supervision focuses on the budgetary execution and project implementation rather than on the achievement of the programme objectives as a whole.

Court’s recommendations : the Court recommends that the Commission should establish a detailed needs-assessment showing the progress of the programmes, the activities still to be performed and an overall financing plan identifying the funding sources. Before further spending takes place, t he Commission should analyse the resources available and the expected benefits . This should lead in turn to objectives being aligned with the resources and to performance indicators which can subsequently be monitored and reported on as necessary.

Further financial assistance after 2013 should be based on an evaluation of its EU added value, identifying the specific activities to be financed taking account of other funding facilities, such as Structural Funds .

Documents
2011/09/22
   EP -

Documents

  • Non-legislative basic document: N7-0041/2012
  • Non-legislative basic document published: N7-0041/2012
  • Non-legislative basic document: N7-0041/2012
AmendmentsDossier
193 2012/2017(DEC)
2012/05/09 CONT 172 amendments...
source: PE-487.976
2012/12/07 CONT 21 amendments...
source: PE-501.976

History

(these mark the time of scraping, not the official date of the change)

docs
  • date: 2012-02-08T00:00:00 docs: title: N7-0041/2012 summary: PURPOSE: to present the ECA special report 16/2011 on EU financial assistance for the decommissioning of nuclear plants in Bulgaria, Lithuania and Slovakia. CONTENT: in order to increase nuclear safety, Bulgaria, Lithuania and Slovakia committed themselves within their EU accession negotiations to the early closure and subsequent decommissioning of eight non-upgradeable nuclear reactors. Recognizing the exceptional social, economic and financial burden of their commitments, the EU provided financial assistance to the three country-programmes (EUR 2 850 million overall for the 1999-2013 period). This special report deals with the implementation of the decommissioning programmes from 1999 up to the end of 2010. The audit examined whether EU funded actions have been designed in accord with identified needs and carried out as planned, and whether the governance arrangements have been adequate. Court’s conclusions : the Court found that while Bulgaria, Lithuania and Slovakia have closed the reactors in line with their commitment, and important milestones have been achieved in decommissioning, the main process is still ahead and its finalisation faces a significant funding shortfall (around EUR 2.5 billion). The Court notes the following: the identification of decommissioning activities is still in progress; major infrastructure projects face delays and cost-overruns; cost estimates are not complete in the absence of key information on radioactive waste and/or the facilities and technologies required for their treatment; a broad variety of activities to mitigate the consequences of the nuclear reactors’ early closure has been financed but the degree of mitigation achieved is not known; there is no comprehensive needs-assessment, prioritization and setting of specific objectives. Responsibilities are diffused. The Commission’s supervision focuses on the budgetary execution and project implementation rather than on the achievement of the programme objectives as a whole. Court’s recommendations : the Court recommends that the Commission should establish a detailed needs-assessment showing the progress of the programmes, the activities still to be performed and an overall financing plan identifying the funding sources. Before further spending takes place, t he Commission should analyse the resources available and the expected benefits . This should lead in turn to objectives being aligned with the resources and to performance indicators which can subsequently be monitored and reported on as necessary. Further financial assistance after 2013 should be based on an evaluation of its EU added value, identifying the specific activities to be financed taking account of other funding facilities, such as Structural Funds . type: Non-legislative basic document body: CofA
events/0/date
Old
2012-02-08T00:00:00
New
2012-02-07T00:00:00
events/1/type
Old
Committee referral announced in Parliament, 1st reading/single reading
New
Committee referral announced in Parliament
procedure/legal_basis/0
Rules of Procedure EP 99
procedure/legal_basis/0
Rules of Procedure EP 93
activities
  • date: 2012-02-08T00:00:00 docs: type: Non-legislative basic document published title: N7-0041/2012 body: EC commission: DG: url: http://ec.europa.eu/dgs/budget/ title: Budget Commissioner: ŠEMETA Algirdas type: Non-legislative basic document published
  • date: 2012-02-16T00:00:00 body: EP type: Committee referral announced in Parliament, 1st reading/single reading committees: body: EP shadows: group: S&D name: BALČYTIS Zigmantas group: Verts/ALE name: STAES Bart group: ECR name: CZARNECKI Ryszard group: GUE/NGL name: SØNDERGAARD Søren Bo group: EFD name: ANDREASEN Marta group: NI name: EHRENHAUSER Martin responsible: True committee: CONT date: 2011-09-22T00:00:00 committee_full: Budgetary Control rapporteur: group: PPE name: MARINESCU Marian-Jean body: EP responsible: False committee_full: Industry, Research and Energy committee: ITRE
commission
  • body: EC dg: Budget commissioner: ŠEMETA Algirdas
events
  • date: 2012-02-08T00:00:00 type: Non-legislative basic document published body: EC docs: title: N7-0041/2012 summary: PURPOSE: to present the ECA special report 16/2011 on EU financial assistance for the decommissioning of nuclear plants in Bulgaria, Lithuania and Slovakia. CONTENT: in order to increase nuclear safety, Bulgaria, Lithuania and Slovakia committed themselves within their EU accession negotiations to the early closure and subsequent decommissioning of eight non-upgradeable nuclear reactors. Recognizing the exceptional social, economic and financial burden of their commitments, the EU provided financial assistance to the three country-programmes (EUR 2 850 million overall for the 1999-2013 period). This special report deals with the implementation of the decommissioning programmes from 1999 up to the end of 2010. The audit examined whether EU funded actions have been designed in accord with identified needs and carried out as planned, and whether the governance arrangements have been adequate. Court’s conclusions : the Court found that while Bulgaria, Lithuania and Slovakia have closed the reactors in line with their commitment, and important milestones have been achieved in decommissioning, the main process is still ahead and its finalisation faces a significant funding shortfall (around EUR 2.5 billion). The Court notes the following: the identification of decommissioning activities is still in progress; major infrastructure projects face delays and cost-overruns; cost estimates are not complete in the absence of key information on radioactive waste and/or the facilities and technologies required for their treatment; a broad variety of activities to mitigate the consequences of the nuclear reactors’ early closure has been financed but the degree of mitigation achieved is not known; there is no comprehensive needs-assessment, prioritization and setting of specific objectives. Responsibilities are diffused. The Commission’s supervision focuses on the budgetary execution and project implementation rather than on the achievement of the programme objectives as a whole. Court’s recommendations : the Court recommends that the Commission should establish a detailed needs-assessment showing the progress of the programmes, the activities still to be performed and an overall financing plan identifying the funding sources. Before further spending takes place, t he Commission should analyse the resources available and the expected benefits . This should lead in turn to objectives being aligned with the resources and to performance indicators which can subsequently be monitored and reported on as necessary. Further financial assistance after 2013 should be based on an evaluation of its EU added value, identifying the specific activities to be financed taking account of other funding facilities, such as Structural Funds .
  • date: 2012-02-16T00:00:00 type: Committee referral announced in Parliament, 1st reading/single reading body: EP
links
other
  • body: EC dg: url: http://ec.europa.eu/dgs/budget/ title: Budget commissioner: ŠEMETA Algirdas
procedure/dossier_of_the_committee
Old
CONT/7/08851
New
  • CONT/7/08851
procedure/legal_basis/0
Rules of Procedure EP 93
procedure/legal_basis/0
Rules of Procedure of the European Parliament EP 093
procedure/subject
Old
  • 3.60.04 Nuclear energy, industry and safety
  • 8.70.03 Budgetary control and discharge, implementation of the budget
  • 8.70.03.06 2011 discharge
New
3.60.04
Nuclear energy, industry and safety
8.70.03
Budgetary control and discharge, implementation of the budget
8.70.03.07
Previous discharges
activities/0/type
Old
Non-legislative basic document
New
Non-legislative basic document published
activities/1/committees/0/rapporteur/0/group
Old
EPP
New
PPE
activities/1/committees/0/rapporteur/0/mepref
Old
4de186d90fb8127435bdc0fd
New
4f1ad96bb819f207b3000016
activities/1/committees/0/shadows/0/mepref
Old
4de183700fb8127435bdbc15
New
4f1ac627b819f25efd000021
activities/1/committees/0/shadows/1/mepref
Old
4de188650fb8127435bdc331
New
4f1adb8fb819f207b30000cf
activities/1/committees/0/shadows/2/mepref
Old
4de183f10fb8127435bdbcdc
New
4f1ac75eb819f25efd000082
activities/1/committees/0/shadows/3/mepref
Old
4de1888a0fb8127435bdc36a
New
4f1adb84b819f207b30000cb
activities/1/committees/0/shadows/4/mepref
Old
4de182e40fb8127435bdbb4b
New
4f1ac5e7b819f25efd00000a
activities/1/committees/0/shadows/5/mepref
Old
4de1847f0fb8127435bdbd9f
New
4f1ac7b8b819f25efd0000a5
activities/2
date
2012-05-09T00:00:00
docs
type: Amendments tabled in committee title: PE487.976
body
EP
type
Amendments tabled in committee
committees/0/rapporteur/0/group
Old
EPP
New
PPE
committees/0/rapporteur/0/mepref
Old
4de186d90fb8127435bdc0fd
New
4f1ad96bb819f207b3000016
committees/0/shadows/0/mepref
Old
4de183700fb8127435bdbc15
New
4f1ac627b819f25efd000021
committees/0/shadows/1/mepref
Old
4de188650fb8127435bdc331
New
4f1adb8fb819f207b30000cf
committees/0/shadows/2/mepref
Old
4de183f10fb8127435bdbcdc
New
4f1ac75eb819f25efd000082
committees/0/shadows/3/mepref
Old
4de1888a0fb8127435bdc36a
New
4f1adb84b819f207b30000cb
committees/0/shadows/4/mepref
Old
4de182e40fb8127435bdbb4b
New
4f1ac5e7b819f25efd00000a
committees/0/shadows/5/mepref
Old
4de1847f0fb8127435bdbd9f
New
4f1ac7b8b819f25efd0000a5
procedure/legal_basis/0
Old
Rules of Procedure of the European Parliament EP 076
New
Rules of Procedure of the European Parliament EP 093
activities/2
date
2012-04-04T00:00:00
docs
url: http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE487.675 type: Committee draft report title: PE487.675
body
EP
type
Committee draft report
activities/2/date
Old
2012-05-15T00:00:00
New
2012-05-09T00:00:00
activities/2/docs/0/url
http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE487.976
activities/4
date
2012-12-07T00:00:00
docs
url: http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE501.976 type: Amendments tabled in committee title: PE501.976
body
EP
type
Amendments tabled in committee
procedure/stage_reached
Old
Awaiting committee decision
New
Procedure lapsed or withdrawn
procedure/stage_reached
Old
Awaiting Parliament 1st reading / single reading / budget 1st stage
New
Awaiting committee decision
activities/2
date
2012-04-04T00:00:00
docs
url: http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE487.675 type: Committee draft report title: PE487.675
body
EP
type
Committee draft report
activities/2/date
Old
2012-12-07T00:00:00
New
2012-04-04T00:00:00
activities/2/docs/0/title
Old
PE501.976
New
PE487.675
activities/2/docs/0/type
Old
Amendments tabled in committee
New
Committee draft report
activities/2/docs/0/url
Old
http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE501.976
New
http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE487.675
activities/2/type
Old
Amendments tabled in committee
New
Committee draft report
activities/3/date
Old
2013-01-21T00:00:00
New
2012-05-15T00:00:00
activities/3/docs
  • url: http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE487.976 type: Amendments tabled in committee title: PE487.976
activities/3/type
Old
Vote scheduled in committee, 1st reading/single reading
New
Amendments tabled in committee
activities/4/date
Old
2012-05-15T00:00:00
New
2012-12-07T00:00:00
activities/4/docs/0/title
Old
PE487.976
New
PE501.976
activities/4/docs/0/url
Old
http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE487.976
New
http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE501.976
activities/0/docs/0/text/0
Old

PURPOSE: to present the ECA special report 16/2011 on EU financial assistance for the decommissioning of nuclear plants in Bulgaria, Lithuania and Slovakia.

CONTENT: in order to increase nuclear safety, Bulgaria, Lithuania and Slovakia committed themselves within their EU accession negotiations to the early closure and subsequent decommissioning of eight non-upgradeable nuclear reactors.

Recognizing the exceptional social, economic and financial burden of their commitments, the EU provided financial assistance to the three country-programmes (EUR 2 850 million overall for the 1999-2013 period).

This special report deals with the implementation of the decommissioning programmes from 1999 up to the end of 2010. The audit examined whether EU funded actions have been designed in accord with identified needs and carried out as planned, and whether the governance arrangements have been adequate.

Court's conclusions: the Court found that while Bulgaria, Lithuania and Slovakia have closed the reactors in line with their commitment, and important milestones have been achieved in decommissioning, the main process is still ahead and its finalisation faces a significant funding shortfall (around EUR 2.5 billion).

The Court notes the following:

  • the identification of decommissioning activities is still in progress;
  • major infrastructure projects face delays and cost-overruns;
  • cost estimates are not complete in the absence of key information on radioactive waste and/or the facilities and technologies required for their treatment;
  • a broad variety of activities to mitigate the consequences of the nuclear reactors' early closure has been financed but the degree of mitigation achieved is not known;
  • there is no comprehensive needs-assessment, prioritization and setting of specific objectives. Responsibilities are diffused. The Commission's supervision focuses on the budgetary execution and project implementation rather than on the achievement of the programme objectives as a whole.

Court's recommendations: the Court recommends that the Commission should establish a detailed needs-assessment showing the progress of the programmes, the activities still to be performed and an overall financing plan identifying the funding sources. Before further spending takes place, the Commission should analyse the resources available and the expected benefits. This should lead in turn to objectives being aligned with the resources and to performance indicators which can subsequently be monitored and reported on as necessary.

Further financial assistance after 2013 should be based on an evaluation of its EU added value, identifying the specific activities to be financed taking account of other funding facilities, such as Structural Funds.

New

PURPOSE: to present the ECA special report 16/2011 on EU financial assistance for the decommissioning of nuclear plants in Bulgaria, Lithuania and Slovakia.

CONTENT: in order to increase nuclear safety, Bulgaria, Lithuania and Slovakia committed themselves within their EU accession negotiations to the early closure and subsequent decommissioning of eight non-upgradeable nuclear reactors.

Recognizing the exceptional social, economic and financial burden of their commitments, the EU provided financial assistance to the three country-programmes (EUR 2 850 million overall for the 1999-2013 period).

This special report deals with the implementation of the decommissioning programmes from 1999 up to the end of 2010. The audit examined whether EU funded actions have been designed in accord with identified needs and carried out as planned, and whether the governance arrangements have been adequate.

Court’s conclusions: the Court found that while Bulgaria, Lithuania and Slovakia have closed the reactors in line with their commitment, and important milestones have been achieved in decommissioning, the main process is still ahead and its finalisation faces a significant funding shortfall (around EUR 2.5 billion).

The Court notes the following:

  • the identification of decommissioning activities is still in progress;
  • major infrastructure projects face delays and cost-overruns;
  • cost estimates are not complete in the absence of key information on radioactive waste and/or the facilities and technologies required for their treatment;
  • a broad variety of activities to mitigate the consequences of the nuclear reactors’ early closure has been financed but the degree of mitigation achieved is not known;
  • there is no comprehensive needs-assessment, prioritization and setting of specific objectives. Responsibilities are diffused. The Commission’s supervision focuses on the budgetary execution and project implementation rather than on the achievement of the programme objectives as a whole.

Court’s recommendations: the Court recommends that the Commission should establish a detailed needs-assessment showing the progress of the programmes, the activities still to be performed and an overall financing plan identifying the funding sources. Before further spending takes place, the Commission should analyse the resources available and the expected benefits. This should lead in turn to objectives being aligned with the resources and to performance indicators which can subsequently be monitored and reported on as necessary.

Further financial assistance after 2013 should be based on an evaluation of its EU added value, identifying the specific activities to be financed taking account of other funding facilities, such as Structural Funds.

activities/0/docs/0/text/0
Old

PURPOSE: to present the ECA special report 16/2011 on EU financial assistance for the decommissioning of nuclear plants in Bulgaria, Lithuania and Slovakia.

CONTENT: in order to increase nuclear safety, Bulgaria, Lithuania and Slovakia committed themselves within their EU accession negotiations to the early closure and subsequent decommissioning of eight non-upgradeable nuclear reactors.

Recognizing the exceptional social, economic and financial burden of their commitments, the EU provided financial assistance to the three country-programmes (EUR 2 850 million overall for the 1999-2013 period).

This special report deals with the implementation of the decommissioning programmes from 1999 up to the end of 2010. The audit examined whether EU funded actions have been designed in accord with identified needs and carried out as planned, and whether the governance arrangements have been adequate.

Court's conclusions: the Court found that while Bulgaria, Lithuania and Slovakia have closed the reactors in line with their commitment, and important milestones have been achieved in decommissioning, the main process is still ahead and its finalisation faces a significant funding shortfall (around EUR 2.5 billion).

The Court notes the following:

  • the identification of decommissioning activities is still in progress;
  • major infrastructure projects face delays and cost-overruns;
  • cost estimates are not complete in the absence of key information on radioactive waste and/or the facilities and technologies required for their treatment;
  • a broad variety of activities to mitigate the consequences of the nuclear reactors' early closure has been financed but the degree of mitigation achieved is not known;
  • there is no comprehensive needs-assessment, prioritization and setting of specific objectives. Responsibilities are diffused. The Commission's supervision focuses on the budgetary execution and project implementation rather than on the achievement of the programme objectives as a whole.

Court's recommendations: the Court recommends that the Commission should establish a detailed needs-assessment showing the progress of the programmes, the activities still to be performed and an overall financing plan identifying the funding sources. Before further spending takes place, the Commission should analyse the resources available and the expected benefits. This should lead in turn to objectives being aligned with the resources and to performance indicators which can subsequently be monitored and reported on as necessary.

Further financial assistance after 2013 should be based on an evaluation of its EU added value, identifying the specific activities to be financed taking account of other funding facilities, such as Structural Funds.

New

PURPOSE: to present the ECA special report 16/2011 on EU financial assistance for the decommissioning of nuclear plants in Bulgaria, Lithuania and Slovakia.

CONTENT: in order to increase nuclear safety, Bulgaria, Lithuania and Slovakia committed themselves within their EU accession negotiations to the early closure and subsequent decommissioning of eight non-upgradeable nuclear reactors.

Recognizing the exceptional social, economic and financial burden of their commitments, the EU provided financial assistance to the three country-programmes (EUR 2 850 million overall for the 1999-2013 period).

This special report deals with the implementation of the decommissioning programmes from 1999 up to the end of 2010. The audit examined whether EU funded actions have been designed in accord with identified needs and carried out as planned, and whether the governance arrangements have been adequate.

Court's conclusions: the Court found that while Bulgaria, Lithuania and Slovakia have closed the reactors in line with their commitment, and important milestones have been achieved in decommissioning, the main process is still ahead and its finalisation faces a significant funding shortfall (around EUR 2.5 billion).

The Court notes the following:

  • the identification of decommissioning activities is still in progress;
  • major infrastructure projects face delays and cost-overruns;
  • cost estimates are not complete in the absence of key information on radioactive waste and/or the facilities and technologies required for their treatment;
  • a broad variety of activities to mitigate the consequences of the nuclear reactors' early closure has been financed but the degree of mitigation achieved is not known;
  • there is no comprehensive needs-assessment, prioritization and setting of specific objectives. Responsibilities are diffused. The Commission's supervision focuses on the budgetary execution and project implementation rather than on the achievement of the programme objectives as a whole.

Court's recommendations: the Court recommends that the Commission should establish a detailed needs-assessment showing the progress of the programmes, the activities still to be performed and an overall financing plan identifying the funding sources. Before further spending takes place, the Commission should analyse the resources available and the expected benefits. This should lead in turn to objectives being aligned with the resources and to performance indicators which can subsequently be monitored and reported on as necessary.

Further financial assistance after 2013 should be based on an evaluation of its EU added value, identifying the specific activities to be financed taking account of other funding facilities, such as Structural Funds.

activities/5
date
2013-01-21T00:00:00
body
EP
type
Vote scheduled in committee, 1st reading/single reading
activities/2
date
2012-04-04T00:00:00
docs
url: http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE487.675 type: Committee draft report title: PE487.675
body
EP
type
Committee draft report
activities/2/date
Old
2012-12-07T00:00:00
New
2012-04-04T00:00:00
activities/2/docs/0/title
Old
PE501.976
New
PE487.675
activities/2/docs/0/type
Old
Amendments tabled in committee
New
Committee draft report
activities/2/docs/0/url
Old
http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE501.976
New
http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE487.675
activities/2/type
Old
Amendments tabled in committee
New
Committee draft report
activities/3/date
Old
2013-01-21T00:00:00
New
2012-05-15T00:00:00
activities/3/docs
  • url: http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE487.976 type: Amendments tabled in committee title: PE487.976
activities/3/type
Old
Vote scheduled in committee, 1st reading/single reading
New
Amendments tabled in committee
activities/4/date
Old
2012-05-15T00:00:00
New
2012-12-07T00:00:00
activities/4/docs/0/title
Old
PE487.976
New
PE501.976
activities/4/docs/0/url
Old
http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE487.976
New
http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE501.976
procedure/title
Old
Special Report No 16/2011 (2011 discharge): EU financial assistance for the decommissioning of nuclear plants in Bulgaria, Lithuania and Slovakia: achievements and future challenges
New
Special report 16/2011 (2011 discharge): EU financial assistance for the decommissioning of nuclear plants in Bulgaria, Lithuania and Slovakia: achievements and future challenges
activities/5
date
2013-01-21T00:00:00
body
EP
type
Vote scheduled in committee, 1st reading/single reading
activities/4/docs/0/url
http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE501.976
activities/2/date
Old
2013-01-22T00:00:00
New
2012-04-04T00:00:00
activities/2/docs
  • url: http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE487.675 type: Committee draft report title: PE487.675
activities/2/type
Old
Vote scheduled in committee, 1st reading/single reading
New
Committee draft report
activities/4/date
Old
2012-04-04T00:00:00
New
2012-12-07T00:00:00
activities/4/docs/0/title
Old
PE487.675
New
PE501.976
activities/4/docs/0/type
Old
Committee draft report
New
Amendments tabled in committee
activities/4/docs/0/url
http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE487.675
activities/4/type
Old
Committee draft report
New
Amendments tabled in committee
activities/0
body
EP
date
2012-02-08T00:00:00
type
Date
activities/2/date
Old
2012-05-03T00:00:00
New
2012-04-04T00:00:00
activities/2/docs
  • url: http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE487.675 type: Committee draft report title: PE487.675
activities/2/type
Old
Deadline Amendments
New
Committee draft report
activities/3
date
2012-04-04T00:00:00
docs
url: http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE487.675 type: Committee draft report title: PE487.675
body
EP
type
Committee draft report
activities/6
body
EP
date
2012-11-27T00:00:00
type
EP 1R Committee
activities/6/type
Old
Vote scheduled in committee, 1st reading/single reading
New
EP 1R Committee
activities/7
date
2013-01-22T00:00:00
body
EP
type
Vote scheduled in committee, 1st reading/single reading
activities/3
date
2012-04-04T00:00:00
docs
url: http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE487.675 type: Committee draft report title: PE487.675
body
EP
type
Committee draft report
activities/3/date
Old
2012-11-06T00:00:00
New
2012-04-04T00:00:00
activities/3/docs
  • url: http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE487.675 type: Committee draft report title: PE487.675
activities/3/type
Old
EP 1R Committee
New
Committee draft report
activities/6
body
EP
date
2012-11-06T00:00:00
type
EP 1R Committee
activities/7/date
Old
2012-11-06T00:00:00
New
2012-11-27T00:00:00
activities/3
date
2012-04-04T00:00:00
docs
url: http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE487.675 type: Committee draft report title: PE487.675
body
EP
type
Committee draft report
activities/3/date
Old
2012-12-11T00:00:00
New
2012-04-04T00:00:00
activities/3/docs
  • url: http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE487.675 type: Committee draft report title: PE487.675
activities/3/type
Old
EP 1R Plenary
New
Committee draft report
activities/8
body
EC
date
2012-12-11T00:00:00
type
Prev DG PRES
commission
DG: url: http://ec.europa.eu/dgs/budget/ title: Budget Commissioner: ŠEMETA Algirdas
activities/7/type
Old
Indicative plenary sitting date, 1st reading/single reading
New
EP 1R Plenary
activities/8
body
EC
date
2012-12-11T00:00:00
type
Prev DG PRES
commission
DG: url: http://ec.europa.eu/dgs/budget/ title: Budget Commissioner: ŠEMETA Algirdas
activities/3
date
2012-04-04T00:00:00
docs
url: http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE487.675 type: Committee draft report title: PE487.675
body
EP
type
Committee draft report
activities/3/date
Old
2012-09-26T00:00:00
New
2012-04-04T00:00:00
activities/3/docs
  • url: http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE487.675 type: Committee draft report title: PE487.675
activities/3/type
Old
Vote scheduled in committee, 1st reading/single reading
New
Committee draft report
activities/6/type
Old
EP 1R Committee
New
Vote scheduled in committee, 1st reading/single reading
activities/5
date
2012-05-15T00:00:00
docs
url: http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE487.976 type: Amendments tabled in committee title: PE487.976
body
EP
type
Amendments tabled in committee
activities/6
date
2012-09-26T00:00:00
body
EP
type
Vote scheduled in committee, 1st reading/single reading
activities/7/type
Old
Vote scheduled in committee, 1st reading/single reading
New
EP 1R Committee
activities/2/committees/0/shadows/2
group
ECR
name
CZARNECKI Ryszard
committees/0/shadows/2
group
ECR
name
CZARNECKI Ryszard
activities/1
date
2012-02-08T00:00:00
docs
type: Non-legislative basic document published title: N7-0041/2012
type
Non-legislative basic document
body
EC
commission
DG: url: http://ec.europa.eu/dgs/budget/ title: Budget Commissioner: ŠEMETA Algirdas
activities/1/date
Old
2012-10-25T00:00:00
New
2012-02-08T00:00:00
activities/1/docs
  • type: Non-legislative basic document published title: N7-0041/2012
activities/1/type
Old
Prev DG PRES
New
Non-legislative basic document
activities/3
date
2012-04-04T00:00:00
docs
url: http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE487.675 type: Committee draft report title: PE487.675
body
EP
type
Committee draft report
activities/3/date
Old
2012-10-25T00:00:00
New
2012-04-04T00:00:00
activities/3/docs
  • url: http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE487.675 type: Committee draft report title: PE487.675
activities/3/type
Old
EP 1R Plenary
New
Committee draft report
activities/5
body
EP
date
2012-09-26T00:00:00
type
EP 1R Committee
activities/5
body
EP
date
2012-09-26T00:00:00
type
EP 1R Committee
activities/6/type
Old
Indicative plenary sitting date, 1st reading/single reading
New
EP 1R Plenary
activities/7
body
EC
date
2012-10-25T00:00:00
type
Prev DG PRES
commission
DG: url: http://ec.europa.eu/dgs/budget/ title: Budget Commissioner: ŠEMETA Algirdas
activities/8/date
Old
2012-09-26T00:00:00
New
2012-11-06T00:00:00
activities/9
date
2012-12-11T00:00:00
body
EP
type
Indicative plenary sitting date, 1st reading/single reading
activities/1/docs/0/text/0
Old

PURPOSE: to present the ECA special report 16/2011 on EU financial assistance for the decommissioning of nuclear plants in Bulgaria, Lithuania and Slovakia.

CONTENT: in order to increase nuclear safety, Bulgaria, Lithuania and Slovakia committed themselves within their EU accession negotiations to the early closure and subsequent decommissioning of eight non-upgradeable nuclear reactors.

Recognizing the exceptional social, economic and financial burden of their commitments, the EU provided financial assistance to the three country-programmes (EUR 2 850 million overall for the 1999-2013 period).

This special report deals with the implementation of the decommissioning programmes from 1999 up to the end of 2010. The audit examined whether EU funded actions have been designed in accord with identified needs and carried out as planned, and whether the governance arrangements have been adequate.

Court’s conclusions: the Court found that while Bulgaria, Lithuania and Slovakia have closed the reactors in line with their commitment, and important milestones have been achieved in decommissioning, the main process is still ahead and its finalisation faces a significant funding shortfall (around EUR 2.5 billion).

The Court notes the following:

  • the identification of decommissioning activities is still in progress;
  • major infrastructure projects face delays and cost-overruns;
  • cost estimates are not complete in the absence of key information on radioactive waste and/or the facilities and technologies required for their treatment;
  • a broad variety of activities to mitigate the consequences of the nuclear reactors’ early closure has been financed but the degree of mitigation achieved is not known;
  • there is no comprehensive needs-assessment, prioritization and setting of specific objectives. Responsibilities are diffused. The Commission’s supervision focuses on the budgetary execution and project implementation rather than on the achievement of the programme objectives as a whole.

Court’s recommendations: the Court recommends that the Commission should establish a detailed needs-assessment showing the progress of the programmes, the activities still to be performed and an overall financing plan identifying the funding sources. Before further spending takes place, the Commission should analyse the resources available and the expected benefits. This should lead in turn to objectives being aligned with the resources and to performance indicators which can subsequently be monitored and reported on as necessary.

Further financial assistance after 2013 should be based on an evaluation of its EU added value, identifying the specific activities to be financed taking account of other funding facilities, such as Structural Funds.

New

PURPOSE: to present the ECA special report 16/2011 on EU financial assistance for the decommissioning of nuclear plants in Bulgaria, Lithuania and Slovakia.

CONTENT: in order to increase nuclear safety, Bulgaria, Lithuania and Slovakia committed themselves within their EU accession negotiations to the early closure and subsequent decommissioning of eight non-upgradeable nuclear reactors.

Recognizing the exceptional social, economic and financial burden of their commitments, the EU provided financial assistance to the three country-programmes (EUR 2 850 million overall for the 1999-2013 period).

This special report deals with the implementation of the decommissioning programmes from 1999 up to the end of 2010. The audit examined whether EU funded actions have been designed in accord with identified needs and carried out as planned, and whether the governance arrangements have been adequate.

Court's conclusions: the Court found that while Bulgaria, Lithuania and Slovakia have closed the reactors in line with their commitment, and important milestones have been achieved in decommissioning, the main process is still ahead and its finalisation faces a significant funding shortfall (around EUR 2.5 billion).

The Court notes the following:

  • the identification of decommissioning activities is still in progress;
  • major infrastructure projects face delays and cost-overruns;
  • cost estimates are not complete in the absence of key information on radioactive waste and/or the facilities and technologies required for their treatment;
  • a broad variety of activities to mitigate the consequences of the nuclear reactors' early closure has been financed but the degree of mitigation achieved is not known;
  • there is no comprehensive needs-assessment, prioritization and setting of specific objectives. Responsibilities are diffused. The Commission's supervision focuses on the budgetary execution and project implementation rather than on the achievement of the programme objectives as a whole.

Court's recommendations: the Court recommends that the Commission should establish a detailed needs-assessment showing the progress of the programmes, the activities still to be performed and an overall financing plan identifying the funding sources. Before further spending takes place, the Commission should analyse the resources available and the expected benefits. This should lead in turn to objectives being aligned with the resources and to performance indicators which can subsequently be monitored and reported on as necessary.

Further financial assistance after 2013 should be based on an evaluation of its EU added value, identifying the specific activities to be financed taking account of other funding facilities, such as Structural Funds.

procedure/legal_basis
  • Rules of Procedure of the European Parliament EP 076
procedure/subject/1
8.70.03 Budgetary control and discharge, implementation of the budget
activities/3
date
2012-04-04T00:00:00
docs
url: http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE487.675 type: Committee draft report title: PE487.675
body
EP
type
Committee draft report
activities/3/date
Old
2012-10-23T00:00:00
New
2012-04-04T00:00:00
activities/3/docs
  • url: http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE487.675 type: Committee draft report title: PE487.675
activities/3/type
Old
EP 1R Plenary
New
Committee draft report
activities/7
body
EC
date
2012-10-23T00:00:00
type
Prev DG PRES
commission
DG: url: http://ec.europa.eu/dgs/budget/ title: Budget Commissioner: ŠEMETA Algirdas
activities/6/date
Old
2012-07-09T00:00:00
New
2012-10-23T00:00:00
activities/6/type
Old
EP 1R Committee
New
EP 1R Plenary
activities/7
body
EC
date
2012-10-23T00:00:00
type
Prev DG PRES
commission
DG: url: http://ec.europa.eu/dgs/budget/ title: Budget Commissioner: ŠEMETA Algirdas
activities/8/date
Old
2012-10-23T00:00:00
New
2012-10-25T00:00:00
activities/5/type
Old
Vote scheduled in committee, 1st reading/single reading
New
EP 1R Committee
activities/6
date
2012-09-26T00:00:00
body
EP
type
Vote scheduled in committee, 1st reading/single reading
activities/3
date
2012-04-04T00:00:00
docs
url: http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE487.675 type: Committee draft report title: PE487.675
body
EP
type
Committee draft report
activities/3/date
Old
2012-09-26T00:00:00
New
2012-04-04T00:00:00
activities/3/docs
  • url: http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE487.675 type: Committee draft report title: PE487.675
activities/3/type
Old
EP 1R Committee
New
Committee draft report
activities/3
date
2012-04-04T00:00:00
docs
url: http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE487.675 type: Committee draft report title: PE487.675
body
EP
type
Committee draft report
activities/3/date
Old
2012-07-04T00:00:00
New
2012-04-04T00:00:00
activities/3/docs
  • url: http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE487.675 type: Committee draft report title: PE487.675
activities/3/type
Old
EP 1R Plenary
New
Committee draft report
activities/5/date
Old
2012-09-26T00:00:00
New
2012-07-09T00:00:00
activities/6/body
Old
EC
New
EP
activities/6/commission
  • DG: url: http://ec.europa.eu/dgs/budget/ title: Budget Commissioner: ŠEMETA Algirdas
activities/6/date
Old
2012-07-04T00:00:00
New
2012-09-26T00:00:00
activities/6/type
Old
Prev DG PRES
New
EP 1R Committee
activities/5
body
EP
date
2012-07-04T00:00:00
type
EP 1R Plenary
activities/6
body
EC
date
2012-07-04T00:00:00
type
Prev DG PRES
commission
DG: url: http://ec.europa.eu/dgs/budget/ title: Budget Commissioner: ŠEMETA Algirdas
activities/8/date
Old
2012-07-04T00:00:00
New
2012-10-23T00:00:00
activities/3
date
2012-04-04T00:00:00
docs
url: http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE487.675 type: Committee draft report title: PE487.675
body
EP
type
Committee draft report
activities/3/date
Old
2012-05-30T00:00:00
New
2012-04-04T00:00:00
activities/3/docs
  • url: http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE487.675 type: Committee draft report title: PE487.675
activities/3/type
Old
Vote scheduled in committee, 1st reading/single reading
New
Committee draft report
activities/6/date
Old
2012-05-29T00:00:00
New
2012-09-26T00:00:00
activities/6/type
Old
EP 1R Committee
New
Vote scheduled in committee, 1st reading/single reading
activities/2/committees/0/shadows
  • group: S&D name: BALČYTIS Zigmantas
  • group: Verts/ALE name: STAES Bart
  • group: GUE/NGL name: SØNDERGAARD Søren Bo
  • group: EFD name: ANDREASEN Marta
  • group: NI name: EHRENHAUSER Martin
committees/0/shadows
  • group: S&D name: BALČYTIS Zigmantas
  • group: Verts/ALE name: STAES Bart
  • group: GUE/NGL name: SØNDERGAARD Søren Bo
  • group: EFD name: ANDREASEN Marta
  • group: NI name: EHRENHAUSER Martin
activities/7/date
Old
2012-07-03T00:00:00
New
2012-07-04T00:00:00
activities/5/type
Old
Vote scheduled in committee, 1st reading/single reading
New
EP 1R Committee
activities/6
date
2012-05-30T00:00:00
body
EP
type
Vote scheduled in committee, 1st reading/single reading
procedure/legal_basis
  • Rules of Procedure of the European Parliament EP 076
activities/3/docs/0/url
http://www.europarl.europa.eu/sides/getDoc.do?type=COMPARL&mode=XML&language=EN&reference=PE487.675
procedure/title
Old
Special Report No 16/2011 (Discharge 2011): EU financial assistance for the decommissioning of nuclear plants in Bulgaria, Lithuania and Slovakia: achievements and future challenges
New
Special Report No 16/2011 (2011 discharge): EU financial assistance for the decommissioning of nuclear plants in Bulgaria, Lithuania and Slovakia: achievements and future challenges
activities/4/date
Old
2012-04-30T00:00:00
New
2012-05-03T00:00:00
activities/1/docs/0/text
  • PURPOSE: to present the ECA special report 16/2011 on EU financial assistance for the decommissioning of nuclear plants in Bulgaria, Lithuania and Slovakia.

    CONTENT: in order to increase nuclear safety, Bulgaria, Lithuania and Slovakia committed themselves within their EU accession negotiations to the early closure and subsequent decommissioning of eight non-upgradeable nuclear reactors.

    Recognizing the exceptional social, economic and financial burden of their commitments, the EU provided financial assistance to the three country-programmes (EUR 2 850 million overall for the 1999-2013 period).

    This special report deals with the implementation of the decommissioning programmes from 1999 up to the end of 2010. The audit examined whether EU funded actions have been designed in accord with identified needs and carried out as planned, and whether the governance arrangements have been adequate.

    Court’s conclusions: the Court found that while Bulgaria, Lithuania and Slovakia have closed the reactors in line with their commitment, and important milestones have been achieved in decommissioning, the main process is still ahead and its finalisation faces a significant funding shortfall (around EUR 2.5 billion).

    The Court notes the following:

    • the identification of decommissioning activities is still in progress;
    • major infrastructure projects face delays and cost-overruns;
    • cost estimates are not complete in the absence of key information on radioactive waste and/or the facilities and technologies required for their treatment;
    • a broad variety of activities to mitigate the consequences of the nuclear reactors’ early closure has been financed but the degree of mitigation achieved is not known;
    • there is no comprehensive needs-assessment, prioritization and setting of specific objectives. Responsibilities are diffused. The Commission’s supervision focuses on the budgetary execution and project implementation rather than on the achievement of the programme objectives as a whole.

    Court’s recommendations: the Court recommends that the Commission should establish a detailed needs-assessment showing the progress of the programmes, the activities still to be performed and an overall financing plan identifying the funding sources. Before further spending takes place, the Commission should analyse the resources available and the expected benefits. This should lead in turn to objectives being aligned with the resources and to performance indicators which can subsequently be monitored and reported on as necessary.

    Further financial assistance after 2013 should be based on an evaluation of its EU added value, identifying the specific activities to be financed taking account of other funding facilities, such as Structural Funds.

activities/3
date
2012-04-04T00:00:00
docs
type: Committee draft report title: PE487.675
body
EP
type
Committee draft report
activities/1/commission/0
DG
Commissioner
ŠEMETA Algirdas
other/0
body
EC
dg
commissioner
ŠEMETA Algirdas
activities
  • body: EP date: 2012-02-08T00:00:00 type: Date
  • date: 2012-02-08T00:00:00 docs: type: Non-legislative basic document published title: N7-0041/2012 type: Non-legislative basic document body: EC commission:
  • date: 2012-02-16T00:00:00 body: EP type: Committee referral announced in Parliament, 1st reading/single reading committees: body: EP responsible: True committee: CONT date: 2011-09-22T00:00:00 committee_full: Budgetary Control rapporteur: group: EPP name: MARINESCU Marian-Jean body: EP responsible: False committee_full: Industry, Research and Energy committee: ITRE
  • body: EP date: 2012-04-30T00:00:00 type: Deadline Amendments
  • date: 2012-05-29T00:00:00 body: EP type: Vote scheduled in committee, 1st reading/single reading
  • date: 2012-07-03T00:00:00 body: EP type: Indicative plenary sitting date, 1st reading/single reading
committees
  • body: EP responsible: True committee: CONT date: 2011-09-22T00:00:00 committee_full: Budgetary Control rapporteur: group: EPP name: MARINESCU Marian-Jean
  • body: EP responsible: False committee_full: Industry, Research and Energy committee: ITRE
links
other
    procedure
    dossier_of_the_committee
    CONT/7/08851
    geographical_area
    reference
    2012/2017(DEC)
    title
    Special Report No 16/2011 (Discharge 2011): EU financial assistance for the decommissioning of nuclear plants in Bulgaria, Lithuania and Slovakia: achievements and future challenges
    legal_basis
    Rules of Procedure of the European Parliament EP 076
    stage_reached
    Awaiting Parliament 1st reading / single reading / budget 1st stage
    type
    DEC - Discharge procedure
    subject