2023/0080(BUD) Draft amending budget 1/2023: technical adjustments stemming from the political agreements reached on several legislative proposals, including with respect to REPowerEU, the Carbon Border Adjustment Mechanism and the Union Secure Connectivity programme
Next event: Indicative plenary sitting date 2023/06/12

Progress: Preparatory phase in Parliament

RoleCommitteeRapporteurShadows
Lead BUDG KELLER Fabienne (icon: Renew Renew) LEWANDOWSKI Janusz (icon: EPP EPP), NEGRESCU Victor (icon: S&D S&D), GUERREIRO Francisco (icon: Verts/ALE Verts/ALE), KUHS Joachim (icon: ID ID), RZOŃCA Bogdan (icon: ECR ECR), PAPADIMOULIS Dimitrios (icon: GUE/NGL GUE/NGL)

Events

2023/06/12
   Indicative plenary sitting date
2023/05/23
   EP - Vote in committee
2023/05/16
   CSL - Council position on draft budget
Documents
2023/05/15
   CSL - Council position on draft budget published
Documents
2023/05/11
   EP - Amendments tabled in committee
Documents
2023/04/13
   EP - Committee draft report
Documents
2023/03/28
   EP - KELLER Fabienne (Renew) appointed as rapporteur in BUDG
2023/03/16
   EC - Commission draft budget
2023/03/16
   EC - Commission draft budget published
Details

PURPOSE: presentation by the Commission of Draft Amending Budget (DAB) No 1 for the year 2023.

CONTENT: Draft Amending Budget (DAB) No 1 for the year 2023 aims at introducing the necessary technical changes to the 2023 budget stemming from the political agreements reached on several legislative proposals, in particular with respect to REPowerEU, the Carbon Border Adjustment Mechanism (CBAM) and the Union Secure Connectivity programme.

Overall, the net impact of DAB 1 on expenditure corresponds to an increase of EUR 52.6 million in commitment appropriations . No additional payment appropriations are requested.

(1) REPowerEU

To address new challenges, on 18 May 2022 the Commission proposed to reinforce the firepower of the Recovery and Resilience Facility Regulation (RRF) through the REPowerEU plan.

The Regulation on the creation of dedicated REPowerEU chapters in the recovery and resilience plans defines specific REPowerEU objectives that should be addressed by the investments and reforms to be included in the existing recovery and resilience plans (RRPs). In addition, the Regulation provides for additional sources of dedicated funding to finance the relevant measures. This includes additional revenue from auctioning of allowances from the Emissions Trading System under Directive 2003/87/EC as well as from voluntary transfers from the Brexit Adjustment Reserve (BAR).

In order to allow the Commission to make the budgetary commitments in a timely manner upon the adoption of the Council implementing decisions, the Commission proposes to make all the necessary additional adjustments to the budget nomenclature and budget remarks in DAB 1, following the adoption of the REPowerEU plan and Regulation with targeted amendments to the Recovery and Resilience Facility Regulation (RRF), the Emissions Trading Schemes (ETS) Directive as well as the Brexit Adjustment Reserve (BAR) Regulation.

(2) Carbon border adjustment mechanism (CBAM)

The final agreement reached by the European Parliament and the Council in December 2022 on the establishment of the Mechanism is based on a centralised governance model, which requires heavy involvement of the Commission in the implementation and the development and maintenance of a substantial IT system. At the same time, the co-legislators did not retain the option of financing CBAM from external assigned revenue accruing from the Emissions Trading System. Therefore, the increased costs for the IT system will have to be financed from the margin under the expenditure ceiling of heading 3 (Natural Resources and Environment), whereas the additional Commission staff will have to be financed under heading 7.

The Commission proposed to create a new budget line for CBAM in heading 3 with a level of respectively EUR 4.1 million in commitment appropriations and EUR 1.6 million in payment appropriations and to delete the existing budget line in heading 1, while adding the appropriations to the corresponding margin under heading 1.

As regards staffing , the Commission recalled that the final agreement reached by the co-legislators on the establishment of the carbon border adjustment mechanism (CBAM) has evolved significantly in terms of the human resources required for its implementation within the Commission, compared to the legislative financial statement which accompanied the original proposal, which was based on a decentralised model of implementation.

The additional Commission human resources required by the final agreement endorsed by the colegislators will not allow the Commission to respect the principle of stable staffing and will require additional resources, to be authorised by the European Parliament and the Council during the annual budget procedure along with the related budgetary appropriations.

The Commission is now asking for an additional 16 posts in its operating establishment plan and four contract agents in 2023 , as well as a corresponding amount of EUR 1.5 million to cover the related administrative expenditure in heading 7, assuming recruitment on average mid-year.

(3) Union secure connectivity programme

In the final trilogue on 23 November 2022, the co-legislators agreed to increase the financing of the Union Secure Connectivity initiative by EUR 50 million from the unallocated margin under the expenditure ceiling of Heading 1. To implement this agreement, the Commission proposes to include in DAB 1 an amount of EUR 50 million in commitment appropriations , which will contribute to the launch of procurement procedures in 2023. The current level of payment appropriations in the 2023 budget is considered sufficient to cover this year’s payment needs.

In particular, DAB 1 covers the following elements:

- adjusting the EU contribution and/or staff numbers of the Anti-Money Laundering Authority (AMLA), the European Union Agency for the Cooperation of Energy Regulators (ACER), the Agency for support to the Body of European Regulators for Electronic Communications (BEREC) and the European Chemicals Agency (ECHA) to take account of changes in their mandates;

- adjusting the establishment plan of the Health and Digital Executive Agency (HaDEA) to take account of a minor change in the staff structure of the executive agency;

- increasing the level of appropriations of the European Data Protection Supervisor (EDPS) to finance legal fees following an increase of litigation cases relating to the application of the General Data Protection Regulation.

Documents

  • Council position on draft budget: 08566/2023
  • Council position on draft budget published: 08566/2023
  • Amendments tabled in committee: PE746.728
  • Committee draft report: PE746.642
  • Commission draft budget: COM(2023)0150
  • Commission draft budget: EUR-Lex
  • Commission draft budget published: COM(2023)0150
  • Commission draft budget published: EUR-Lex
  • Commission draft budget: COM(2023)0150 EUR-Lex
  • Committee draft report: PE746.642
  • Amendments tabled in committee: PE746.728
  • Council position on draft budget: 08566/2023
AmendmentsDossier
1 2023/0080(BUD)
2023/05/11 BUDG 1 amendments...
source: 746.728

History

(these mark the time of scraping, not the official date of the change)

commission
  • body: EC dg: Budget commissioner: HAHN Johannes
events/3
date
2023-06-01T00:00:00
type
Committee referral announced in Parliament
body
EP
procedure/dossier_of_the_committee
  • BUDG/9/11559
procedure/stage_reached
Old
Preparatory phase in Parliament
New
Awaiting committee decision
events/1/date
Old
2023-05-16T00:00:00
New
2023-05-15T00:00:00
events/1/date
Old
2023-05-15T00:00:00
New
2023-05-16T00:00:00
events/2
date
2023-05-23T00:00:00
type
Vote in committee
body
EP
procedure/Other legal basis
Rules of Procedure EP 159
docs/3
date
2023-05-16T00:00:00
docs
title: 08566/2023
type
Council position on draft budget
body
CSL
events/1
date
2023-05-15T00:00:00
type
Council position on draft budget published
body
CSL
docs
title: 08566/2023
docs/2
date
2023-05-11T00:00:00
docs
url: https://www.europarl.europa.eu/doceo/document/BUDG-AM-746728_EN.html title: PE746.728
type
Amendments tabled in committee
body
EP
events/0/summary
  • PURPOSE: presentation by the Commission of Draft Amending Budget (DAB) No 1 for the year 2023.
  • CONTENT: Draft Amending Budget (DAB) No 1 for the year 2023 aims at introducing the necessary technical changes to the 2023 budget stemming from the political agreements reached on several legislative proposals, in particular with respect to REPowerEU, the Carbon Border Adjustment Mechanism (CBAM) and the Union Secure Connectivity programme.
  • Overall, the net impact of DAB 1 on expenditure corresponds to an increase of EUR 52.6 million in commitment appropriations . No additional payment appropriations are requested.
  • (1) REPowerEU
  • To address new challenges, on 18 May 2022 the Commission proposed to reinforce the firepower of the Recovery and Resilience Facility Regulation (RRF) through the REPowerEU plan.
  • The Regulation on the creation of dedicated REPowerEU chapters in the recovery and resilience plans defines specific REPowerEU objectives that should be addressed by the investments and reforms to be included in the existing recovery and resilience plans (RRPs). In addition, the Regulation provides for additional sources of dedicated funding to finance the relevant measures. This includes additional revenue from auctioning of allowances from the Emissions Trading System under Directive 2003/87/EC as well as from voluntary transfers from the Brexit Adjustment Reserve (BAR).
  • In order to allow the Commission to make the budgetary commitments in a timely manner upon the adoption of the Council implementing decisions, the Commission proposes to make all the necessary additional adjustments to the budget nomenclature and budget remarks in DAB 1, following the adoption of the REPowerEU plan and Regulation with targeted amendments to the Recovery and Resilience Facility Regulation (RRF), the Emissions Trading Schemes (ETS) Directive as well as the Brexit Adjustment Reserve (BAR) Regulation.
  • (2) Carbon border adjustment mechanism (CBAM)
  • The final agreement reached by the European Parliament and the Council in December 2022 on the establishment of the Mechanism is based on a centralised governance model, which requires heavy involvement of the Commission in the implementation and the development and maintenance of a substantial IT system. At the same time, the co-legislators did not retain the option of financing CBAM from external assigned revenue accruing from the Emissions Trading System. Therefore, the increased costs for the IT system will have to be financed from the margin under the expenditure ceiling of heading 3 (Natural Resources and Environment), whereas the additional Commission staff will have to be financed under heading 7.
  • The Commission proposed to create a new budget line for CBAM in heading 3 with a level of respectively EUR 4.1 million in commitment appropriations and EUR 1.6 million in payment appropriations and to delete the existing budget line in heading 1, while adding the appropriations to the corresponding margin under heading 1.
  • As regards staffing , the Commission recalled that the final agreement reached by the co-legislators on the establishment of the carbon border adjustment mechanism (CBAM) has evolved significantly in terms of the human resources required for its implementation within the Commission, compared to the legislative financial statement which accompanied the original proposal, which was based on a decentralised model of implementation.
  • The additional Commission human resources required by the final agreement endorsed by the colegislators will not allow the Commission to respect the principle of stable staffing and will require additional resources, to be authorised by the European Parliament and the Council during the annual budget procedure along with the related budgetary appropriations.
  • The Commission is now asking for an additional 16 posts in its operating establishment plan and four contract agents in 2023 , as well as a corresponding amount of EUR 1.5 million to cover the related administrative expenditure in heading 7, assuming recruitment on average mid-year.
  • (3) Union secure connectivity programme
  • In the final trilogue on 23 November 2022, the co-legislators agreed to increase the financing of the Union Secure Connectivity initiative by EUR 50 million from the unallocated margin under the expenditure ceiling of Heading 1. To implement this agreement, the Commission proposes to include in DAB 1 an amount of EUR 50 million in commitment appropriations , which will contribute to the launch of procurement procedures in 2023. The current level of payment appropriations in the 2023 budget is considered sufficient to cover this year’s payment needs.
  • In particular, DAB 1 covers the following elements:
  • - adjusting the EU contribution and/or staff numbers of the Anti-Money Laundering Authority (AMLA), the European Union Agency for the Cooperation of Energy Regulators (ACER), the Agency for support to the Body of European Regulators for Electronic Communications (BEREC) and the European Chemicals Agency (ECHA) to take account of changes in their mandates;
  • - adjusting the establishment plan of the Health and Digital Executive Agency (HaDEA) to take account of a minor change in the staff structure of the executive agency;
  • - increasing the level of appropriations of the European Data Protection Supervisor (EDPS) to finance legal fees following an increase of litigation cases relating to the application of the General Data Protection Regulation.
committees/0/shadows/2
name
GUERREIRO Francisco
group
Group of the Greens/European Free Alliance
abbr
Verts/ALE
docs/1
date
2023-04-13T00:00:00
docs
url: https://www.europarl.europa.eu/doceo/document/BUDG-PR-746642_EN.html title: PE746.642
type
Committee draft report
body
EP
committees/0
type
Responsible Committee
body
EP
committee_full
Budgets
committee
BUDG
associated
False
rapporteur
name: KELLER Fabienne date: 2023-03-28T00:00:00 group: Renew Europe group abbr: Renew
shadows
committees/0
type
Responsible Committee
body
EP
committee_full
Budgets
committee
BUDG
associated
False
rapporteur
name: ŞTEFĂNUȚĂ Nicolae date: 2023-03-20T00:00:00 group: Group of the Greens/European Free Alliance abbr: Verts/ALE
shadows
docs/0
date
2023-03-16T00:00:00
docs
type
Commission draft budget
body
EC
docs/0
date
2023-03-16T00:00:00
docs
type
Commission draft budget
body
EC
events/0
date
2023-03-16T00:00:00
type
Commission draft budget published
body
EC
docs
events/0
date
2023-03-16T00:00:00
type
Commission draft budget published
body
EC
docs
forecasts
  • date: 2023-06-12T00:00:00 title: Indicative plenary sitting date
docs/0/type
Old
Non-legislative basic document
New
Commission draft budget
events/0/type
Old
Non-legislative basic document published
New
Commission draft budget published
procedure/subtype
Old
Mobilisation of funds
New
Budget
committees/0/shadows
  • name: LEWANDOWSKI Janusz group: Group of European People's Party abbr: EPP
  • name: NEGRESCU Victor group: Group of Progressive Alliance of Socialists and Democrats abbr: S&D
  • name: KELLER Fabienne group: Renew Europe group abbr: Renew
  • name: KUHS Joachim group: Identity and Democracy abbr: ID
  • name: RZOŃCA Bogdan group: European Conservatives and Reformists Group abbr: ECR
  • name: PAPADIMOULIS Dimitrios group: The Left group in the European Parliament - GUE/NGL abbr: GUE/NGL
committees/0/rapporteur
  • name: ŞTEFĂNUȚĂ Nicolae date: 2023-03-20T00:00:00 group: Group of the Greens/European Free Alliance abbr: Verts/ALE
docs/0/docs/0
url
https://eur-lex.europa.eu/smartapi/cgi/sga_doc?smartapi!celexplus!prod!DocNumber&lg=EN&type_doc=COMfinal&an_doc=2023&nu_doc=0150
title
EUR-Lex
events/0/docs/0
url
https://eur-lex.europa.eu/smartapi/cgi/sga_doc?smartapi!celexplus!prod!DocNumber&lg=EN&type_doc=COMfinal&an_doc=2023&nu_doc=0150
title
EUR-Lex